Permit: T06OT02523
Permit Details
Apply Date:
09/28/2006
Applicant:
JAMES LI
Description:
FLOODPLAIN USE PERMIT: FOR ADDN:DTCHED BDRM & BTHR
Permit Reviews
Permit Number - T06OT02523
Permit Status: Final
Permit Description: FLOODPLAIN USE PERMIT: FOR ADDN:DTCHED BDRM & BTHR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/12/2007 | RESUBMITTAL | 02/16/2007 | COMPLETED |
| 09/28/2006 | PLANS OK TO SUBMIT - FLOODPLAIN | 09/28/2006 | COMPLETED |
| 09/28/2006 | FLOODPLAIN | 11/21/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06OT02523
Permit Status: Final
Permit Description: FLOODPLAIN USE PERMIT: FOR ADDN:DTCHED BDRM & BTHR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/16/2007 | January 16, 2007 FLOODPLAIN USE PERMIT NO.: T06OT02523 (Second Review) RELATED PROJECT: T06CM04005 ADDRESS: 6417 E. Baylor Dr. APPLICANT: James Li The applicant is authorized to use a portion of the City of Tucson property described as (legal description): YALE ESTATES LOT 16 BLK 20 1. This permit is for the purpose of construction of a single-family residence within a mapped Flood Hazard Area, Zone X (Shaded), as shown on the Flood Insurance Rate Map (FIRM), Community Panel No. 040076-04019C-2253K, effective date February 8, 1999. 2. The proposed structure is impacted by the regulatory floodplain. For purposes of this permit, the following elevation requirements apply: Base Flood Elevation (BFE) = 0.5 feet above highest adjacent natural grade Regulatory Flood Elevation (RFE) = 1.5 feet above highest adjacent natural grade The top of the lowest finished floor (FFE) shall be elevated at or above the Regulatory Flood Elevation (RFE). Service facilities, such as electrical equipment, shall be constructed at or above the RFE and either be placed on flood proof materials or be adequately flood proofed. Prior to the pouring of the first slab or finish floor installation, a Building-Under-Construction Elevation Certificate, completed and certified by an Arizona Registered Land Surveyor, must be returned to the Engineering Division of the Development Services Department. A hold will be placed on the slab inspection (P2S) until the Elevation Certificate has been returned and approved. Prior to any final inspections, a Finished Construction Elevation Certificate, completed and certified by an Arizona Registered Land Surveyor, must be returned to the Engineering Division. A hold will be placed on the final inspection (P2F) until the Elevation Certificate has been returned and approved. 3. Any additional improvements will require a separate Floodplain Use Permit prior to construction. |