Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address NEW:
306 N ALVERNON WY 09
Apply Date:
12/14/2006
Applicant:
KEVIN HOWARD ARCHITECTS
Description:
HOTEL
Contractors:
  • HICKAM ARNOLD DEVELOPMENT L L C

Permit Reviews

Permit Number - T06CM06335
Permit Status: C of o
Permit Description: HOTEL
Start Date Submittal Complete Date Status  
01/08/2008 RESUBMITTAL 01/16/2008 COMPLETED Review Details
02/21/2008 3RD PARTY REVIEW-REVISION/OTHER 02/21/2008 COMPLETED Review Details
03/13/2008 3RD PARTY REVIEW-REVISION/OTHER 07/22/2008 COMPLETED Review Details
04/13/2007 POST 3RD PARTY REVIEW 04/18/2007 COMPLETED Review Details
05/07/2007 POST 3RD PARTY REVIEW 06/12/2007 COMPLETED Review Details
07/22/2008 3RD PARTY REVIEW-REVISION/OTHER 07/22/2008 COMPLETED Review Details
08/27/2007 POST 3RD PARTY REVIEW 09/20/2007 COMPLETED Review Details
10/02/2008 3RD PARTY REVIEW-REVISION/OTHER-2ND 10/07/2008 COMPLETED Review Details
10/23/2007 RESUBMITTAL 01/08/2008 COMPLETED Review Details
11/03/2008 3RD PARTY REVIEW-REVISION/OTHER 11/05/2008 COMPLETED Review Details
12/14/2006 PLANS OK TO SUBMIT - 3RD PARTY 12/19/2006 COMPLETED Review Details
12/19/2006 3RD PARTY REVIEW-COMMERCIAL 04/13/2007 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T06CM06335
Permit Status: C of o
Permit Description: HOTEL
Total Outstanding Activity Conditions - 1
Date Name
12/14/2006 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T06CM06335
Permit Description: HOTEL
Total Completed Inspections - 42
Date Description Inspector Results Comments
04/14/2008 ELECTRIC - UNDERGROUND DSANTACR Approved IVRS - Inspection :*
OK 4" POWER & COMM. TO BLD #6
05/12/2008 ELECTRIC - UFER RHOLLAND Approved IVRS - Inspection :*
OK 4/0 TO REBAR & 20 + ' IN FOOTING
05/13/2008 BUILDING PRE-SLAB JBURGE Approved OK TO POUR SLAB
05/13/2008 EXCAVATION/LAYOUT REBAR & ZON JBURGE Approved IVRS - Inspection :*
CONTINUOUS FOOTINGS AND COLUMNS -- OK TO POUR
05/13/2008 PLUMBING - PRE SLAB BBENEDON Approved IVRS - Inspection :*
05/13/2008 PLUMBING - ROUGH, SOIL BBENEDON Approved IVRS - Inspection :*
05/23/2008 PLUMBING - SEWER HCS CONNECT BBENEDON Approved IVRS - Inspection :*
06/13/2008 ROOF NAILING JBURGE Approved IVRS - Inspection :*
OK TO DRY IN
06/24/2008 EXT METAL CLIPS/EXT SHEATHING JBURGE Approved IVRS - Inspection :*
OK TO COVER
06/30/2008 ELECTRIC - INTERMEDIATE RHOLLAND Approved IVRS - Inspection :*
1. FINISH PANEL ROOM
2. NM NOT ALLOWED IN RETURN AIR

OK ROUGH EXCEPT ELECTRIC ROOM
06/30/2008 ELECTRIC - ABOVE CEILING RHOLLAND Approved IVRS - Inspection :*
08/07/2008 PLUMBING - ABOVE CEILING BBENEDON Approved IVRS - Inspection :
See detailed listing on site.| 999*
1) WATER PIPING NOT SIZED PER PLAN
2) DWV NO TEST
08/07/2008 PLUMBING - GAS PRESSURE TEST BBENEDON Approved IVRS - Inspection :*
08/07/2008 PLUMBING - ROOF DRAINS BBENEDON Approved IVRS - Inspection :*
08/28/2008 STUCCO MESH JBURGE Approved IVRS - Inspection :*
OK TO STUCCO
08/28/2008 PLUMBING - INTERMEDIATE BBENEDON Approved IVRS - Inspection :*
WATER PIPING INSULATION AND STRAPPING OK
10/16/2008 SHEET ROCK NAILING JBURGE Approved IVRS - Inspection :*
OK TO TAPE THROUGHOUT
10/16/2008 BUILDING ABOVE CEILING JBURGE Approved IVRS - Inspection :*
ALL HARD CEILINGS
10/16/2008 FRAMING JBURGE Approved IVRS - Inspection :*
11/14/2008 MECHANICAL - ABOVE CEILING MRAMBER Approved IVRS - Inspection :*
11/14/2008 MECHANICAL - INTERMEDIATE MRAMBER Approved IVRS - Inspection :*
02/20/2009 ELECTRIC - FINAL RMORENO Approved IVRS - Inspection :*
BUILDING AND LIGHTING OK
02/20/2009 ELECTRIC - CONSTRUCTION POWER RMORENO Approved
02/20/2009 ELECTRIC - RECONNECT RMORENO Approved
02/20/2009 ELECTRIC - OUTDOOR LIGHTING RMORENO Approved
02/20/2009 U VALUE FOR WINDOW JBURGE Approved IVRS - Inspection :*
02/20/2009 FIRE SPKLR - UG, PIPING, HYDRO LTHOMAS Approved
02/20/2009 FIRE SPKLR - UG PIPING FLUSH LTHOMAS Approved
02/20/2009 FIRE SPKLR - OH PIPING & HYDRO LTHOMAS Approved
02/20/2009 FIRE SPKLR - FINAL LTHOMAS Approved
02/20/2009 OUTDOOR LIGHTING FINAL RMORENO Approved IVRS - Inspection :*
02/27/2009 SIGN - FINAL LHANLY Approved IVRS - Inspection :*
02/27/2009 FIRE - FINAL LTHOMAS Approved
03/02/2009 PLUMBING - FINAL BBENEDON Approved IVRS - Inspection :*
PROVIDE IRRIGATION BACKFLOW ASSEMBLY CERTIFICATION
03/02/2009 MECHANICAL - FINAL MRAMBER Approved IVRS - Inspection :*
03/02/2009 BUILDING - FINAL JBURGE Approved IVRS - Inspection :*
03/02/2009 PLUMBING - GAS PRESS TEST FNL BBENEDON Approved IVRS - Inspection :*
03/03/2009 PLUMBING - YARD WTR LINE/TEST BBENEDON Approved IVRS - Inspection :*
05/19/2010 NPPO - FINAL JFEMLING Approved Approved
05/19/2010 LANDSCAPE - FINAL JFEMLING Approved Approved
05/19/2010 ENGINEERING - FINAL JFEMLING Approved All items complete, approved
06/18/2010 RIGHT OF WAY - FINAL MHERNADE Approved

Documents

File Name Document Type  
TEMP C OF O_03-04-2009.TIF CERT OF OCC VIEW
None CERT OF OCC VIEW
None CONSTRPLANS VIEW
None DOCUMENTS VIEW