Permit: T06CM06294
Permit Details
Status:
C of o
Type:
SINGLE FAMILY NEW
Address:
2093 S TWINKLING STARR DR
Address NEW:
2093 S TWINKLING STARR DR
Apply Date:
12/13/2006
Applicant:
RUBIO ARMANDO
Description:
SFR:NEW R1 - HCS location R2 OSB roof sheathing, pool gas branch & 50A branch for pool R3 Revise (2) braced panels
Permit Reviews
Permit Number - T06CM06294
Permit Status: C of o
Permit Description: SFR:NEW
R1 - HCS location
R2 OSB roof sheathing, pool gas branch & 50A branch for pool
R3 Revise (2) braced panels
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/04/2007 | RESIDENTIAL BLDG/WWM | 01/19/2007 | COMPLETED |
| 02/02/2007 | RESIDENTIAL BLDG/ZONING/ENGINE/WWM | 02/27/2007 | COMPLETED |
| 03/05/2007 | RESUBMITTAL | 03/14/2007 | COMPLETED |
| 03/14/2007 | RESUBMITTAL | 03/19/2007 | COMPLETED |
| 03/19/2007 | RESUBMITTAL | 04/16/2007 | COMPLETED |
| 04/23/2007 | REVISION - - 1ST | 04/23/2007 | COMPLETED |
| 06/25/2007 | REVISION - - 2ND | 06/25/2007 | COMPLETED |
| 07/26/2007 | REVISION - - 3RD | 07/26/2007 | COMPLETED |
| 12/13/2006 | PLANS OK TO SUBMIT - RES | 01/04/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM06294
Permit Status: C of o
Permit Description: SFR:NEW
R1 - HCS location
R2 OSB roof sheathing, pool gas branch & 50A branch for pool
R3 Revise (2) braced panels
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/13/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T06CM06294
Permit Description: SFR:NEW
R1 - HCS location
R2 OSB roof sheathing, pool gas branch & 50A branch for pool
R3 Revise (2) braced panels
Total Completed Inspections - 31
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/24/2007 | PLUMBING - SEWER HCS CONNECT | EDURAZO | Approved | IVRS - Inspection :* |
| 04/24/2007 | PLUMBING - ROUGH, SOIL | EDURAZO | Approved | IVRS - Inspection :* |
| 05/04/2007 | PLUMBING - PRE SLAB | CTREVILL | Approved | IVRS - Inspection :* 1) PENDING 2ND POUR (MASTER AND GARAGE) |
| 05/04/2007 | ELECTRIC - UNDERGROUND | CTREVILL | Approved | IVRS - Inspection :* |
| 05/04/2007 | ELECTRIC - UFER | CTREVILL | Approved | IVRS - Inspection :* |
| 05/18/2007 | BUILDING PRE-SLAB | CTREVILL | Approved | IVRS - Inspection :* |
| 05/18/2007 | STEM WALL/RETAINING WALL | CTREVILL | Approved | IVRS - Inspection :* |
| 05/18/2007 | EXCAVATION/LAYOUT REBAR & ZON | CTREVILL | Approved | IVRS - Inspection :* |
| 05/23/2007 | ELECTRIC - TEMPORARY SERVICE | CRUIZ | Approved | |
| 05/23/2007 | ELECTRIC - CABLE DROP | CRUIZ | Approved | IVRS - Inspection :* |
| 05/24/2007 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED PER C. RUIZ |
| 06/28/2007 | BUILDING ABOVE CEILING | WNORTH | Approved | IVRS - Inspection :* |
| 06/28/2007 | ROOF NAILING | WNORTH | Approved | IVRS - Inspection :* |
| 06/28/2007 | EXT METAL CLIPS/EXT SHEATHING | WNORTH | Approved | IVRS - Inspection :* |
| 07/13/2007 | PLUMBING - YARD WTR LINE/TEST | DWALKER | Approved | IVRS - Inspection :* |
| 07/13/2007 | MECHANICAL - INTERMEDIATE | DWALKER | Approved | IVRS - Inspection :* |
| 07/13/2007 | PLUMBING - GAS PRESSURE TEST | DWALKER | Approved | IVRS - Inspection :* |
| 07/13/2007 | PLUMBING - INTERMEDIATE | DWALKER | Approved | IVRS - Inspection :* |
| 07/13/2007 | ELECTRIC - INTERMEDIATE | DWALKER | Approved | IVRS - Inspection :* |
| 07/16/2007 | STUCCO MESH | DWALKER | Approved | IVRS - Inspection :* |
| 07/16/2007 | FRAMING | DWALKER | Approved | IVRS - Inspection :* |
| 07/27/2007 | SHEET ROCK NAILING | WNORTH | Approved | IVRS - Inspection :* |
| 01/22/2008 | MECHANICAL - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 01/22/2008 | PLUMBING - GAS PRESS TEST FNL | DQUINN | Approved | IVRS - Inspection :* |
| 04/18/2008 | PLUMBING - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
| 04/18/2008 | ELECTRIC - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
| 04/22/2008 | BUILDING - PROGRESS | RCAMACHO | Approved | |
| 04/22/2008 | ELECTRIC - PROGRESS | RCAMACHO | Approved | |
| 04/22/2008 | PLUMBING - PROGRESS | RCAMACHO | Approved | |
| 04/22/2008 | BUILDING - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
| 04/23/2008 | PERMIT FINALED | BFLORES | Approved |