Permit: T06CM05292
Permit Details
Apply Date:
10/06/2006
Applicant:
N/A
Description:
TI: OFFICE PENDING ON TI FOR WAREHOUSE PORTION ON SHELL
Architects:
- KRAMER, JOEL ERIC
Contractors:
- SELLERS AND SONS INC ,
Permit Reviews
Permit Number - T06CM05292
Permit Status: Final
Permit Description: TI: OFFICE
PENDING ON TI FOR WAREHOUSE PORTION ON SHELL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/06/2006 | COMMERCIAL TI | 10/13/2006 | COMPLETED |
| 10/13/2006 | 3RD PARTY REVIEW-COMMERCIAL TI | 11/01/2006 | COMPLETED |
| 11/01/2006 | POST 3RD PARTY REVIEW | 11/03/2006 | COMPLETED |
| 11/03/2006 | RESUBMITTAL | 11/03/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM05292
Permit Status: Final
Permit Description: TI: OFFICE
PENDING ON TI FOR WAREHOUSE PORTION ON SHELL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/06/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T06CM05292
Permit Description: TI: OFFICE
PENDING ON TI FOR WAREHOUSE PORTION ON SHELL
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/17/2006 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* 1) THIS IS TO ALLOW CONTRACTOR TO TIE IN TI DISCONNECT AT SERVICE, CONTRACTOR NOT TO ENERGIZE PANEL "L1" FOR TI UNTIL APPROVED BY INSPECTOR |
| 11/17/2006 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
| 11/17/2006 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED FOR OFFICE PER D. SANTACRUZ |
| 11/20/2006 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* |
| 11/22/2006 | BUILDING ABOVE CEILING | AALEGRIA | Approved | IVRS - Inspection :* |
| 11/22/2006 | FRAMING | AALEGRIA | Approved | IVRS - Inspection :* |
| 12/12/2006 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 12/12/2006 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* 1. CONNECT EXHAUST DUCTS. WILL CHECK ON FINAL. 2. PROVIDE PRIMARY & SECONDARY DRAINS. 3. SECURE STAT WIRE AS PER NEC 4. SECURE FLEX DUCTS & LINE SETS. |
| 12/18/2006 | SHEET ROCK NAILING | AALEGRIA | Approved | IVRS - Inspection :* |
| 12/22/2006 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 12/28/2006 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* 1) OK FOR FINAL |
| 12/29/2006 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* NO ACCESS AT 8:06 BUILDING LOCKED |
| 12/29/2006 | ENGINEERING - FINAL | MAVERY | Approved | No work outside of building. |
| 12/29/2006 | BUILDING - FINAL | AALEGRIA | Approved | IVRS - Inspection :* |
| 12/29/2006 | FIRE - FINAL | LTHOMAS | Approved | |
| 12/29/2006 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 01/04/2007 | NPPO - FINAL | ACONNOR | Approved | PER INSP CARD |
| 01/04/2007 | LANDSCAPE - FINAL | ACONNOR | Approved | PER INSP CARD |
| 01/04/2007 | SIGN - FINAL | JYBARRA | Approved | PER PH CALL |
| 01/04/2007 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER PH CALL |
| 01/04/2007 | PLUMBING - ABOVE CEILING | RLEDONNE | Approved | PER PL FINAL |
| 01/04/2007 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | PER PL FINAL |
| 01/05/2007 | PERMIT FINALED | BFLORES | Approved |