Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T06CM04913
Permit Details
Apply Date:
09/05/2006
Applicant:
CUSTOM PLUS BUILDERS INC ,
Description:
SFR:NEW R1 Relocate window & door
Contractors:
- CUSTOM PLUS BUILDERS INC ,
Permit Reviews
Permit Number - T06CM04913
Permit Status: C of o
Permit Description: SFR:NEW
R1 Relocate window & door
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/05/2007 | REVISION - - 1ST | 02/05/2007 | COMPLETED |
| 09/05/2006 | PLANS OK TO SUBMIT - RES | 09/18/2006 | COMPLETED |
| 09/18/2006 | RESIDENTIAL BLDG/WWM | 10/24/2006 | COMPLETED |
| 10/26/2006 | RESUBMITTAL | 11/14/2006 | COMPLETED |
| 11/14/2006 | RESUBMITTAL | 11/27/2006 | COMPLETED |
| 12/01/2006 | RESUBMITTAL | 12/22/2006 | COMPLETED |
| 12/22/2006 | RESUBMITTAL | 01/09/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM04913
Permit Status: C of o
Permit Description: SFR:NEW
R1 Relocate window & door
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/05/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T06CM04913
Permit Description: SFR:NEW
R1 Relocate window & door
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/13/2007 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | IVRS - Inspection :* |
| 02/21/2007 | ELECTRIC - UNDERGROUND | CTREVILL | Approved | IVRS - Inspection :* |
| 02/21/2007 | ELECTRIC - UFER | CTREVILL | Approved | IVRS - Inspection :* |
| 02/21/2007 | BUILDING PRE-SLAB | CTREVILL | Approved | IVRS - Inspection :* |
| 02/21/2007 | EXCAVATION/LAYOUT REBAR & ZON | CTREVILL | Approved | IVRS - Inspection :* |
| 03/21/2007 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | IVRS - Inspection :* |
| 03/26/2007 | ROOF NAILING | DQUINN | Approved | IVRS - Inspection :* |
| 04/04/2007 | PLUMBING - SEWER HCS CONNECT | WLAHR | Approved | IVRS - Inspection :* |
| 04/26/2007 | TEP CLEARANCE - PM | DQUINN | Approved | ECO CLEARED PER D. QUINN |
| 04/26/2007 | ELECTRIC - TEMPORARY SERVICE | DQUINN | Approved | IVRS - Inspection :* |
| 04/26/2007 | ELECTRIC - CABLE DROP | DQUINN | Approved | IVRS - Inspection :* |
| 04/26/2007 | U VALUE FOR WINDOW | DQUINN | Approved | IVRS - Inspection :* |
| 04/26/2007 | STUCCO MESH | DQUINN | Approved | IVRS - Inspection :* |
| 04/26/2007 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 04/26/2007 | PLUMBING - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 04/26/2007 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 04/26/2007 | FRAMING | DQUINN | Approved | IVRS - Inspection :* |
| 05/03/2007 | SHEET ROCK NAILING | DQUINN | Approved | IVRS - Inspection :* |
| 07/26/2007 | ELECTRIC - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 07/31/2007 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | IVRS - Inspection :* |
| 07/31/2007 | MECHANICAL - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 07/31/2007 | PLUMBING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 08/03/2007 | PLUMBING - PRE SLAB | DQUINN | Approved | |
| 08/03/2007 | BUILDING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 09/18/2007 | GRADING - INTERMEDIATE | JBRUCKME | Approved |