Permit: T06CM04042
Permit Details
Apply Date:
07/11/2006
Applicant:
GAL WITMER
Description:
ALTERNATOR SHOP
Architects:
- PETRICK KEVIN BLAKE
Contractors:
- INNOVATIVE CUSTOM HOMES AND DESIGN L L C
Permit Reviews
Permit Number - T06CM04042
Permit Status: C of o
Permit Description: ALTERNATOR SHOP
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/11/2006 | PLANS OK TO SUBMIT - 3RD PARTY | 07/28/2006 | COMPLETED |
| 07/28/2006 | 3RD PARTY REVIEW-COMMERCIAL TI | 11/08/2006 | COMPLETED |
| 09/16/2013 | REVISION - - 1ST | 09/17/2013 | COMPLETED |
| 09/17/2013 | REVISION - - 1ST | 10/09/2013 | COMPLETED |
| 10/30/2013 | REVISION - - 1ST | 11/04/2013 | COMPLETED |
| 11/04/2013 | REVISION - - 1ST | 11/13/2013 | COMPLETED |
| 11/08/2006 | POST 3RD PARTY REVIEW | 11/21/2006 | COMPLETED |
| 11/13/2013 | REVISION - - 1ST | 11/13/2013 | COMPLETED |
| 12/13/2006 | RESUBMITTAL | 04/24/2007 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T06CM04042
Permit Description: ALTERNATOR SHOP
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/10/2007 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED PER R. HOLLANDER |
| 12/13/2013 | RIGHT OF WAY - FINAL | TWOLFGAN | Approved | |
| 12/16/2013 | NPPO - FINAL | RLEDONNE | Approved | |
| 12/16/2013 | SIGN - FINAL | RLEDONNE | Approved | |
| 12/16/2013 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
| 12/17/2013 | FIRE - FINAL | wmotto | Approved | |
| 12/17/2013 | ENGINEERING - FINAL | RLEDONNE | Approved | NO CHANGE TO PARKING AREA PER LEE RAY. |
| 12/19/2013 | MECHANICAL - FINAL | LHANLY | Approved | |
| 12/19/2013 | MECHANICAL - INTERMEDIATE | LHANLY | Approved | |
| 12/19/2013 | PLUMBING - FINAL | LHANLY | Approved | |
| 12/19/2013 | PLUMBING - YARD WTR LINE/TEST | LHANLY | Approved | |
| 12/19/2013 | PLUMBING - ABOVE CEILING | LHANLY | Approved | |
| 12/19/2013 | PLUMBING - INTERMEDIATE | LHANLY | Approved | |
| 12/19/2013 | PLUMBING - PRE SLAB | LHANLY | Approved | |
| 12/19/2013 | PLUMBING - ROUGH, SOIL | LHANLY | Approved | |
| 12/19/2013 | ELECTRIC - FINAL | LHANLY | Approved | |
| 12/19/2013 | ELECTRIC - INTERMEDIATE | LHANLY | Approved | |
| 12/19/2013 | BUILDING - FINAL | LHANLY | Approved | |
| 12/19/2013 | SHEET ROCK NAILING | LHANLY | Approved | |
| 12/19/2013 | U VALUE FOR WINDOW | LHANLY | Approved | |
| 12/19/2013 | FRAMING | LHANLY | Approved | |
| 12/19/2013 | ROOF NAILING | LHANLY | Approved | |
| 12/19/2013 | FRAMING | blahr | Approved |