Permit: T06CM03784
Permit Details
Apply Date:
06/27/2006
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
SITE/WAREHOUSE
Architects:
- ACORN, KIM BRIAN
Contractors:
- COBRE BUILDING SYSTEMS INC ,
Permit Reviews
Permit Number - T06CM03784
Permit Status: C of o
Permit Description: SITE/WAREHOUSE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/16/2007 | 3RD PARTY REVIEW-REVISION/OTHER | 01/23/2007 | COMPLETED |
| 05/08/2007 | REVISION - SITE | 05/09/2007 | COMPLETED |
| 06/27/2006 | PLANS OK TO SUBMIT - SITE | 06/27/2006 | COMPLETED |
| 06/27/2006 | SITE | 08/24/2006 | COMPLETED |
| 09/25/2006 | RESUBMITTAL - SITE ALL | 10/26/2006 | COMPLETED |
| 09/25/2006 | PLANS OK TO SUBMIT - 3RD PARTY | 09/25/2006 | COMPLETED |
| 09/25/2006 | 3RD PARTY REVIEW-COMMERCIAL | 11/20/2006 | COMPLETED |
| 11/13/2006 | RESUBMITTAL - SITE ALL | 12/04/2006 | COMPLETED |
| 11/20/2006 | POST 3RD PARTY REVIEW | 12/07/2006 | COMPLETED |
| 12/07/2006 | RESUBMITTAL | 12/13/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM03784
Permit Status: C of o
Permit Description: SITE/WAREHOUSE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/27/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T06CM03784
Permit Description: SITE/WAREHOUSE
Total Completed Inspections - 42
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/06/2007 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
| 02/21/2007 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* |
| 02/27/2007 | BUILDING PRE-SLAB | AALEGRIA | Approved | IVRS - Inspection :* 5" CONCRETE SLAB WITH #4 @ 24" O.C EA. WALL CENTERED IN SLAB PLUS HAIRPIN, TURDOWN ON WESTSIDE 18" WIDTH WITH #4 TOP & BOT. AND #3 @ 24" O.C HOOK SPECIAL INSPECTION REPORT IN COMPLIANCE OK TO POUR |
| 02/27/2007 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
| 03/21/2007 | REINFORCED MASONRY PRE-GROUT | AALEGRIA | Approved | IVRS - Inspection :* @ TOPOUT 108'-0" |
| 03/29/2007 | FRAMING | AALEGRIA | Approved | IVRS - Inspection :* INTERIOR PARTITIONS WITH COLD-FORMER STEEL STUDS ON OFFICE AND WOMEN/MEN RESTROOMS OK TO DRYWALL INSTALLATION AFTER ELECTRICAL, MECH & PLUMBING APPROVAL. |
| 04/13/2007 | ROOF NAILING | AALEGRIA | Approved | IVRS - Inspection :* |
| 04/13/2007 | EXT METAL CLIPS/EXT SHEATHING | AALEGRIA | Approved | IVRS - Inspection :* |
| 04/20/2007 | EXCAVATION/LAYOUT REBAR & ZON | AALEGRIA | Approved | IVRS - Inspection :* |
| 04/27/2007 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* |
| 05/02/2007 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* |
| 05/02/2007 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 05/03/2007 | PLUMBING - GAS PRESSURE TEST | RLEDONNE | Approved | IVRS - Inspection :* |
| 05/04/2007 | PLUMBING - ABOVE CEILING | RLEDONNE | Approved | IVRS - Inspection :* |
| 05/04/2007 | SHEET ROCK NAILING | AALEGRIA | Approved | IVRS - Inspection :* |
| 05/04/2007 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | IVRS - Inspection :* |
| 05/07/2007 | FIRE SPKLR - UG PIPING FLUSH | CSCHULTZ | Approved | FLUSHED FOR 2 MINS |
| 05/09/2007 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | 1. PROVIDE LETTER OF TORQUE FOR SES 2. OK GFCI MAIN BREAKER TEST BY F&M USING GENERATOR AND TEST PER INSTRUCTIONS, WITNESSED BY DAN S.C INSPECTOR 3. POST BOND FOR TEMP POWER FOR TESTING. FOR POWER CLEARANCE PRIOR TO FINAL APPROVAL |
| 05/09/2007 | SITE - SEWER | RLEDONNE | Approved | IVRS - Inspection :* |
| 05/09/2007 | PLUMBING - SEWER HCS CONNECT | RLEDONNE | Approved | IVRS - Inspection :* |
| 05/09/2007 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
| 06/01/2007 | ELECTRIC - CONSTRUCTION POWER | RJIROUDE | Approved | IVRS - Inspection :* |
| 06/04/2007 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* OK FOR CEILING TILES |
| 06/04/2007 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER R. JIROUDEK-BOND POSTED #S300-4300-1117 |
| 06/04/2007 | ELECTRIC - TEMP POWER FOR TEST | IVR USER | Approved | IVRS - RI canceled |
| 06/11/2007 | BUILDING ABOVE CEILING | AALEGRIA | Approved | IVRS - Inspection :* |
| 06/20/2007 | PLUMBING - GAS PRESS TEST FNL | RLEDONNE | Approved | IVRS - Inspection :* |
| 06/21/2007 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 06/21/2007 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
| 06/21/2007 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection :* |
| 06/22/2007 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
| 06/26/2007 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
| 06/27/2007 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 06/28/2007 | NPPO - FINAL | ACONNOR | Approved | |
| 06/28/2007 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 07/16/2007 | ENGINEERING - FINAL | MAVERY | Approved | Contractor completed punch list. |
| 07/19/2007 | FIRE - FINAL | CSCHULTZ | Approved | |
| 07/19/2007 | FIRE SPKLR - FINAL | CSCHULTZ | Approved | |
| 08/21/2007 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 08/22/2007 | BUILDING - FINAL | LHANLY | Approved | IVRS - Inspection :* |
| 08/22/2007 | BUILDING - PROGRESS | LHANLY | Approved | IVRS - Inspection :* |
| 08/23/2007 | PERMIT FINALED | BFLORES | Approved |