Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T06CM03635
Permit Details
Apply Date:
06/19/2006
Applicant:
VLADIMIR ZILBERMAN
Description:
TI: RETAIL
Contractors:
- MARKET CONTRACTORS LTD
Permit Reviews
Permit Number - T06CM03635
Permit Status: C of o
Permit Description: TI: RETAIL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/19/2006 | PLANS OK TO SUBMIT - COMM | 06/19/2006 | COMPLETED |
06/19/2006 | 3RD PARTY REVIEW-COMMERCIAL TI | 07/12/2006 | COMPLETED |
07/12/2006 | POST 3RD PARTY REVIEW | 08/10/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM03635
Permit Status: C of o
Permit Description: TI: RETAIL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/19/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T06CM03635
Permit Description: TI: RETAIL
Total Completed Inspections - 26
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/22/2006 | FRAMING | AALEGRIA | Approved | IVRS - Inspection :* |
08/22/2006 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* |
08/23/2006 | ELECTRIC - TEMPORARY SERVICE | DSANTACR | Approved | IVRS - Inspection :* |
08/23/2006 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED FOR UNIT #100 PER D. SANTACRUZ |
08/25/2006 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* ABS REVENT TEST OK |
08/28/2006 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* NO OVERHEAD WATER PER PLANS |
08/28/2006 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
09/12/2006 | BUILDING ABOVE CEILING | AALEGRIA | Approved | IVRS - Inspection :* |
09/12/2006 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | |
09/13/2006 | MECHANICAL - ABOVE CEILING | CWILLIAM | Approved | IVRS - Inspection :* NOTE! FOR FINAL WILL NEED ROOF ACCESS. WILL CHECK FUSING, COND. DRAINS ETC. ON EXISTING AC UNITS. |
09/18/2006 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection :* |
09/18/2006 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
09/18/2006 | FIRE - FINAL | LTHOMAS | Approved | |
09/18/2006 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection :* |
09/20/2006 | ELECTRIC - CONSTRUCTION POWER | DSANTACR | Approved | IVRS - Inspection :* |
09/20/2006 | ELECTRIC - RECONNECT | DSANTACR | Approved | IVRS - Inspection :* |
09/20/2006 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
09/20/2006 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
09/21/2006 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | |
09/26/2006 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
09/26/2006 | BUILDING - FINAL | LHANLY | Approved | IVRS - Inspection :* |
09/26/2006 | SHEET ROCK NAILING | LHANLY | Approved | IVRS - Inspection :* |
09/27/2006 | PLUMBING - ABOVE CEILING | RRICH | Approved | |
09/29/2006 | SIGN - FINAL | CSTEPHEN | Approved | spoke with Julie |
09/29/2006 | PERMIT FINALED | BGRANT | Approved | |
09/29/2006 | ENGINEERING - FINAL | DROBERTS | Approved |