Permit: T06CM03456
Permit Details
Apply Date:
06/12/2006
Applicant:
SHAMBACH, DAVID E.
Description:
TI:STORAGE
Architects:
- SHAMBACH, DAVID E.
Contractors:
- COMPLETE CARPENTRY INC
Permit Reviews
Permit Number - T06CM03456
Permit Status: C of o
Permit Description: TI:STORAGE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/04/2007 | REVISION - - 1ST | 01/04/2007 | COMPLETED |
| 06/12/2006 | PLANS OK TO SUBMIT - 3RD PARTY | 07/25/2006 | COMPLETED |
| 07/24/2006 | COMMERCIAL TI | 08/17/2006 | COMPLETED |
| 09/29/2006 | RESUBMITTAL | 10/17/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM03456
Permit Status: C of o
Permit Description: TI:STORAGE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/12/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T06CM03456
Permit Description: TI:STORAGE
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/15/2006 | FRAMING | AALEGRIA | Approved | IVRS - Inspection :* IN COMPLIANCE WITH APPROVED PLANS SHEET AZ AND SPECIFIC DETAILS. |
| 11/15/2006 | PLUMBING - SEWER HCS CONNECT | BBENEDON | Approved | IVRS - Inspection :* |
| 11/15/2006 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 11/15/2006 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
| 11/16/2006 | PLUMBING - YARD WTR LINE/TEST | RLEDONNE | Approved | IVRS - Inspection :* |
| 11/29/2006 | ELECTRIC - UNDERGROUND | IVR USER | Approved | IVRS - AP canceled |
| 11/30/2006 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* 1. OUTSIDE WALL LIGHT MUST BE FULLY SHADED PER PLAN 2. COMPLETE CONDUIT INSTALL 3. OK GROUNDING BONDS FOR SERVICE. |
| 11/30/2006 | SHEET ROCK NAILING | AALEGRIA | Approved | IVRS - Inspection :* |
| 11/30/2006 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection : See detailed listing on site.| 999* |
| 11/30/2006 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
| 11/30/2006 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
| 12/12/2006 | PLUMBING - PROGRESS | RLEDONNE | Approved | IVRS - Inspection :* FLANGE SECURE TO FLOOR OK |
| 12/19/2006 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | IVRS - Inspection :* |
| 12/20/2006 | TEP CLEARANCE - AM | BFLORES | Approved | TEC PER D.SANTA CRUZ |
| 01/05/2007 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 01/05/2007 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 01/05/2007 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 01/05/2007 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
| 01/10/2007 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 01/10/2007 | BUILDING - FINAL | AALEGRIA | Approved | IVRS - Inspection :* IN COMPLIANCE WITH APPROVED PLANS AND SPEC. ACCORDING WITH TI REVIEWED BY 2003 IBC OK TO OCCUPY |
| 01/10/2007 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 01/10/2007 | FIRE - FINAL | LLAKEY | Approved | |
| 01/10/2007 | NPPO - FINAL | ACONNOR | Approved | N/A |
| 01/10/2007 | LANDSCAPE - FINAL | ACONNOR | Approved | N/A |
| 01/12/2007 | ENGINEERING - FINAL | MAVERY | Approved | Contractor striped out 3 parking spaces. |
| 01/13/2007 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |
| 01/16/2007 | PERMIT FINALED | LJACKSON | Approved |