Permit: T06CM01862
Permit Details
Apply Date:
03/31/2006
Applicant:
STEPHEN MOOS
Description:
NEW WAREHOUSE
Architects:
- STEPHEN MOOS
Contractors:
- WAID CONSTRUCTION INC
Permit Reviews
Permit Number - T06CM01862
Permit Status: C of o
Permit Description: NEW WAREHOUSE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/31/2006 | PLANS OK TO SUBMIT - 3RD PARTY | 03/31/2006 | COMPLETED |
03/31/2006 | 3RD PARTY REVIEW-COMMERCIAL | 05/10/2006 | COMPLETED |
05/10/2006 | POST 3RD PARTY REVIEW | 06/16/2006 | COMPLETED |
06/27/2006 | RESUBMITTAL | 06/30/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM01862
Permit Status: C of o
Permit Description: NEW WAREHOUSE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/31/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T06CM01862
Permit Description: NEW WAREHOUSE
Total Completed Inspections - 35
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/24/2006 | SITE - SEWER | RLEDONNE | Approved | IVRS - Inspection :* |
10/17/2006 | EXCAVATION/LAYOUT REBAR & ZON | AALEGRIA | Approved | IVRS - Inspection :* IN COMPLIANCE WITH APPROVED PLANS MONOLITHIC POUR, DETAIL ON SHEET S2.S3 |
10/17/2006 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
10/17/2006 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* |
10/17/2006 | BUILDING PRE-SLAB | AALEGRIA | Approved | IVRS - Inspection :* |
10/17/2006 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
11/14/2006 | EXT METAL CLIPS/EXT SHEATHING | AALEGRIA | Approved | IVRS - Inspection :* |
12/15/2006 | U VALUE FOR WINDOW | AALEGRIA | Approved | IVRS - Inspection :* U VALUE WINDOWS APPROVED PLUS STUCCO MESH INSTALLATION IN COMPLIANCE WITH REQ. |
02/12/2007 | PLUMBING - YARD WTR LINE/TEST | RLEDONNE | Approved | IVRS - Inspection :* |
05/17/2007 | NPPO - FINAL | ACONNOR | Approved | |
05/17/2007 | LANDSCAPE - FINAL | ACONNOR | Approved | |
05/17/2007 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
10/30/2007 | ENGINEERING - FINAL | JFEMLING | Approved | Approved |
11/02/2007 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | |
04/30/2008 | FRAMING | MHENSON | Approved | IVRS - Inspection :* |
04/30/2008 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* |
05/21/2008 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* OK ABOVE CEILING, RECEIVED LETTER PANEL RELOCATE |
05/21/2008 | BUILDING ABOVE CEILING | MHENSON | Approved | IVRS - Inspection :* |
05/21/2008 | PLUMBING - ABOVE CEILING | RLEDONNE | Approved | IVRS - Inspection :* |
05/21/2008 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* |
05/22/2008 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
05/28/2008 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* OK TO INSTALL TILES |
06/09/2008 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | IVRS - Inspection :* 1) CALL FOR FINAL INSP. AFTER POWER CHECK 2) PROVIDE LETTER FROM OWNER FOR USE OF ALUMINUM CONDUCTORS PER PLAN NOTE |
06/10/2008 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER D. SANTACRUZ |
06/17/2008 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
06/17/2008 | ELECTRIC - TEMPORARY SERVICE | DSANTACR | Approved | IVRS - Inspection :* |
06/17/2008 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection :* |
06/17/2008 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* |
06/17/2008 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection :* |
06/17/2008 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
06/17/2008 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
06/24/2008 | FIRE - FINAL | LTHOMAS | Approved | |
06/25/2008 | BUILDING - FINAL | MHENSON | Approved | IVRS - Inspection :* |
06/25/2008 | ROOF NAILING | MHENSON | Approved | IVRS - Inspection :* |
06/26/2008 | PERMIT FINALED | BFLORES | Approved |