Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T06CM01861
Permit Details
Apply Date:
03/31/2006
Applicant:
STEPHEN MOOS
Description:
NEW WAREHOUSE
Architects:
- STEPHEN MOOS
Contractors:
- WAID CONSTRUCTION INC
Permit Reviews
Permit Number - T06CM01861
Permit Status: C of o
Permit Description: NEW WAREHOUSE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/31/2006 | PLANS OK TO SUBMIT - 3RD PARTY | 03/31/2006 | COMPLETED |
03/31/2006 | PLANS OK TO SUBMIT - SITE | 03/31/2006 | COMPLETED |
03/31/2006 | 3RD PARTY REVIEW-COMMERCIAL | 05/10/2006 | COMPLETED |
05/10/2006 | POST 3RD PARTY REVIEW | 06/16/2006 | COMPLETED |
06/26/2006 | RESUBMITTAL | 06/30/2006 | COMPLETED |
06/30/2006 | RESUBMITTAL | 06/30/2006 | COMPLETED |
09/10/2010 | REVISION - - 1ST | 09/10/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM01861
Permit Status: C of o
Permit Description: NEW WAREHOUSE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/31/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T06CM01861
Permit Description: NEW WAREHOUSE
Total Completed Inspections - 34
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/24/2006 | SITE - SEWER | RLEDONNE | Approved | IVRS - Inspection :* PIPING FOR UNDERGROUND TO BE |
09/13/2006 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* |
09/15/2006 | PLUMBING - YARD WTR LINE/TEST | RLEDONNE | Approved | IVRS - Inspection :* TEST FROM INSIDE LOT 1MIN. FROM SEWER TO TWO-WAY CLEANOUTS EAST OF CAMPBELL & RUNNING EAST WEST. |
10/25/2006 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* OK FOR H20, BLD. STEEL, TELEPHONE, SPRINKLER |
10/25/2006 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
10/26/2006 | BUILDING PRE-SLAB | AALEGRIA | Approved | IVRS - Inspection :* |
10/26/2006 | EXCAVATION/LAYOUT REBAR & ZON | AALEGRIA | Approved | IVRS - Inspection :* |
11/22/2006 | FRAMING | AALEGRIA | Approved | IVRS - Inspection :* |
11/22/2006 | EXT METAL CLIPS/EXT SHEATHING | AALEGRIA | Approved | IVRS - Inspection :* |
12/28/2006 | U VALUE FOR WINDOW | AALEGRIA | Approved | IVRS - Inspection :* |
05/17/2007 | SIGN - FINAL | JYBARRA | Approved | |
05/17/2007 | LANDSCAPE - FINAL | ACONNOR | Approved | |
05/17/2007 | NPPO - FINAL | ACONNOR | Approved | |
05/17/2007 | LANDSCAPE - FINAL | ACONNOR | Approved | |
10/30/2007 | ENGINEERING - FINAL | JFEMLING | Approved | Approved |
11/02/2007 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | |
09/09/2008 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
03/06/2009 | ROOF NAILING | LHANLY | Approved | IVRS - Inspection :* |
08/28/2009 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
09/03/2009 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* PROVIDED RFI FOR ITEMS 8-19-09 |
09/30/2009 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* 1) CLOSET FLANGE OK |
10/06/2009 | BUILDING ABOVE CEILING | GDABBS | Approved | |
10/06/2009 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* 1) MAINTAIN WORKING CLEARANCE A/C DISCONNECT 2) OK ELECTRIC AFTER CORRECTIONS IN ROOM 101 |
10/06/2009 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |
10/06/2009 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
10/09/2009 | ELECTRIC - TEMP POWER FOR TEST | RHOLLAND | Approved | IVRS - Inspection :* |
10/16/2009 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED FOR HOUSE AND #101 PER R. HOLLANDER |
11/05/2009 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
07/28/2010 | FIRE - FINAL | LTHOMAS | Approved | |
09/10/2010 | OUTDOOR LIGHTING FINAL | LHANLY | Approved | |
09/10/2010 | ELECTRIC - FINAL | LHANLY | Approved | |
09/10/2010 | ELECTRIC - TEMPORARY SERVICE | LHANLY | Approved | |
09/10/2010 | ELECTRIC - INTERMEDIATE | LHANLY | Approved | |
09/10/2010 | ELECTRIC - UNDERGROUND | LHANLY | Approved |