Permit: T06CM01023
Permit Details
Status:
C of o
Type:
COMMERCIAL NEW
Address:
4816 E CAMP LOWELL DR
Address NEW:
4816 E CAMP LOWELL DR
Apply Date:
02/21/2006
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
NEW MEDICAL OFFICE LOT 37
Contractors:
- VENTURE WEST CONSTRUCTION L L C
Permit Reviews
Permit Number - T06CM01023
Permit Status: C of o
Permit Description: NEW MEDICAL OFFICE
LOT 37
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/21/2006 | PLANS OK TO SUBMIT - COMM | 02/22/2006 | COMPLETED |
| 02/22/2006 | 3RD PARTY REVIEW-COMMERCIAL | 04/06/2006 | COMPLETED |
| 04/06/2006 | POST 3RD PARTY REVIEW | 05/02/2006 | COMPLETED |
| 05/02/2006 | RESUBMITTAL | 05/03/2006 | COMPLETED |
| 11/30/2006 | 3RD PARTY REVIEW-REVISION/OTHER | 12/06/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM01023
Permit Status: C of o
Permit Description: NEW MEDICAL OFFICE
LOT 37
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/21/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T06CM01023
Permit Description: NEW MEDICAL OFFICE
LOT 37
Total Completed Inspections - 40
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/25/2006 | PLUMBING - SEWER HCS CONNECT | BBENEDON | Approved | IVRS - Inspection :* POST ADDRESS & PERMIT CARD |
| 05/26/2006 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
| 06/27/2006 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* |
| 08/17/2006 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* OK TO DRY IN |
| 08/17/2006 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* |
| 09/01/2006 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | OK TO SHEETROCK ONE SIDE AFTER ELECTRIC INTERMEDIATE OK TO INSULATE AND COMPLETE SHEETROCK |
| 09/01/2006 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
| 09/06/2006 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* OK WALLS AND LIDS |
| 09/14/2006 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved | IVRS - Inspection :* |
| 09/20/2006 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* RECEIVED LETTER FROM ENGINEER |
| 09/20/2006 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* PLEASE ENSURE THAT ALL PENETRATIONS IN SEPARATION WALLS ARE PROPERLY FIRE CAULKED. |
| 09/20/2006 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* OK TO STUCCO |
| 09/20/2006 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
| 10/13/2006 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* FINISH INSTALLING EXHAUST FAN WILL CHECK ON FINAL OK FOR CEILING TILES. |
| 10/13/2006 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* OK TO SET TILES. |
| 10/13/2006 | U VALUE FOR WINDOW | JBURGE | Approved | IVRS - Inspection :* |
| 10/30/2006 | STEM WALL/RETAINING WALL | JBURGE | Approved | IVRS - Inspection :* |
| 11/06/2006 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* CLOSET FLANGES OK |
| 11/13/2006 | SIGN - FINAL | JSONKIN | Approved | IVRS - Inspection :* |
| 11/16/2006 | ELECTRIC - TEMP POWER FOR TEST | RHOLLAND | Approved | IVRS - Inspection :* |
| 11/16/2006 | ELECTRIC - CONSTRUCTION POWER | RHOLLAND | Approved | IVRS - Inspection :* |
| 11/16/2006 | ELECTRIC - CABLE DROP | RHOLLAND | Approved | IVRS - Inspection :* |
| 11/17/2006 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | PER EMAIL |
| 11/17/2006 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED PER R. HOLLANDER |
| 11/22/2006 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* 1) OK FOR FINAL 2) AIR BALANCE QUANTITIES ARE OK |
| 11/22/2006 | FIRE - FINAL | LTHOMAS | Approved | |
| 11/22/2006 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | IVRS - Inspection :* |
| 11/22/2006 | ELECTRIC - UFER | RHOLLAND | Approved | IVRS - Inspection :* |
| 11/22/2006 | SITE - SEWER | BBENEDON | Approved | IVRS - Inspection :* |
| 11/22/2006 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
| 11/22/2006 | NPPO - FINAL | ACONNOR | Approved | |
| 11/22/2006 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 11/29/2006 | ELECTRIC - OUTDOOR LIGHTING | RHOLLAND | Approved | IVRS - Inspection :* |
| 11/29/2006 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* |
| 11/29/2006 | ENGINEERING - FINAL | JBRUCKME | Approved | |
| 11/29/2006 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 12/05/2006 | OUTDOOR LIGHTING FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
| 12/05/2006 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
| 12/05/2006 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 12/06/2006 | PERMIT FINALED | DROBEY | Approved |