Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T06BU01511
Permit Details
Apply Date:
06/14/2006
Applicant:
N/A
Description:
GRADING:2606CY CUT 6401CY FILL
Contractors:
- WILSON CONSTRUCTION
Permit Reviews
Permit Number - T06BU01511
Permit Status: Final
Permit Description: GRADING:2606CY CUT 6401CY FILL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/24/2007 | REVISION - GRADING | 01/24/2007 | COMPLETED |
| 01/24/2007 | REVISION - GRADING | 01/29/2007 | COMPLETED |
| 06/14/2006 | PLANS OK TO SUBMIT - GRADING | 06/14/2006 | COMPLETED |
| 06/14/2006 | GRADING | 07/19/2006 | COMPLETED |
| 08/07/2006 | RESUBMITTAL - GRADING ALL | 09/18/2006 | COMPLETED |
| 09/21/2006 | RESUBMITTAL - GRADING ALL | 10/11/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06BU01511
Permit Status: Final
Permit Description: GRADING:2606CY CUT 6401CY FILL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/14/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T06BU01511
Permit Description: GRADING:2606CY CUT 6401CY FILL
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/06/2006 | NPPO PRE PERMIT INSPECTION | ACONNOR | Approved | |
| 11/13/2006 | ENGINEERING PRE-CONSTRUCTION | MAVERY | Approved | Completed pre-con meeting. |
| 11/15/2006 | STORMWATER INSTALL OF CONTROLS | MRUSSO | Approved | 1) POST A SIGNED COPY OF YOUR NOI AT THE ENTRANCE TO THE SITE. 2) PROVIDE A DESIGNATED CONCRETE/MATERIAL WASH OUT AS SOON AS PRACTICABLE. 3) DOCUMENT ANY CHANGES MADE TO THE APPROVED STORM WATER PLAN, AND PROVIDE TO THE INSPECTOR. 4) PERFORM PERIODIC STORM WATER MAINT. INSPECTIONS PER PLAN, AND DOCUMENT THEM. 5) SWEEP UP ALL TRACKED MATERIAL OFF OF PUBLIC ROADWAYS ROUTINELY. 6) I WILL ADDRESS BANK/SLOPE EROSION LOCATED ON THE NW SIDE OF SITE - WILL FOLLOW UP. |
| 12/28/2006 | STORMWATER FOLLOW-UP INSP | MRUSSO | Approved | RE-ESTABLISH SEDIMENT CONTROLS AROUND THE EXISTING STOCKPILE. |
| 08/22/2007 | GRADING - INTERMEDIATE | MRUSSO | Approved | PROPOSED CHANGES TO DRAINAGE ALONG SOUTH PERIMETER NEED ENGINEER APPROVAL AND CITY OF TUCSON APPROVAL OF CHANGES. CHANGES TO SANITARY SEWER MANHOLE ALONG DRANAGE CHANNEL LOCATED ON NORTH SIDE OF SITE. SHOW DETAIL ON CHANGE. |
| 12/28/2007 | GRADING - FINAL | MRUSSO | Approved | 1) STABILIZE SLOPES, PLACE ROCK RIP RAP AND DG, AND COMPLETE SWALE ALONG EAST AND NORTHEAST SIDE OF BLDG. 2) PROVIDE A STAMPED DRAWING (FROM THE ENGINEER OF RECORD) OF CHANGES MADE TO THE DRAINAGE SWALE ALONG THE SOUTH SIDE OF SITE. 3) PROVIDE A RET/DET BASIN CERTIFICATION STATEMENT FROM THE ENGINEER OF RECORD STATING THAT THE ALL BASINS AND DRAINAGE WAYS WERE BUILT IN ACCORDANCE WITH THE APPROVED GRADING PLAN. 4) RE-INSTALL HC PARKING SIGN AT HC PARKING SPOT. 5) CLEAN OFF SOIL/DEBRIS FROM SIDEWALK, EAST SIDE. 6) COMPLETE TYPE#4 CATCH BASIN, NOTE #14 (SE CORNER). 7) RE-WORK SWALE ON SOUTH SIDE OF BLDG. TIE INTO DRAINAGE. 8) PATCH CURB OPENING ALONG SW CORNER OF SITE. 9) INSTALL TRUNCATED DOMES AT CURB ACCESS RAMP AT NW CORNER OF BLDG. 10) INSTALL 6" SCUPPER THROUGH WALKWAY ALONG NORTH SIDE OF BLDG - TIE INTO ROOF DRAIN. |
| 01/11/2008 | STORMWATER FINAL INSPECTION | MRUSSO | Approved | |
| 01/18/2008 | LANDSCAPE INSPECTION | ACONNOR | Approved |