Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Apply Date:
12/09/2005
Applicant:
ALAN ROBERTS ARCHITECTS
Description:
TI: TANNING SALON

Permit Reviews

Permit Number - T05CM06121
Permit Status: C of o
Permit Description: TI: TANNING SALON
Start Date Submittal Complete Date Status  
02/28/2006 POST 3RD PARTY REVIEW 03/02/2006 COMPLETED Review Details
12/09/2005 PLANS OK TO SUBMIT - 3RD PARTY 12/09/2005 COMPLETED Review Details
12/09/2005 3RD PARTY REVIEW-COMMERCIAL TI 02/28/2006 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T05CM06121
Permit Status: C of o
Permit Description: TI: TANNING SALON
Total Outstanding Activity Conditions - 1
Date Name
12/09/2005 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T05CM06121
Permit Description: TI: TANNING SALON
Total Completed Inspections - 24
Date Description Inspector Results Comments
03/07/2006 FRAMING AQUIROZ Approved IVRS - Inspection :*
04/04/2006 SHEET ROCK NAILING AQUIROZ Approved IVRS - Inspection :*
04/13/2006 PLUMBING - INTERMEDIATE RMYERS Approved IVRS - Inspection :*
1. CORRECTIONS MADE OK.
2. OK TO COVER ALL AREAS.
04/13/2006 PLUMBING - INTERMEDIATE RMYERS Approved IVRS - Inspection :*
1. INSTALL INSULATION PER PLAN.
PERMIT AND PLAN TO BE ON SITE AT ALL TIMES.
05/16/2006 ELECTRIC - TEMPORARY SERVICE CCLEMENS Approved
05/16/2006 ELECTRIC - CABLE DROP CCLEMENS Approved IVRS - Inspection :*
05/17/2006 TEP CLEARANCE - AM JWEATHER Approved ECO CLEARED PER C. CLEMENS
06/01/2006 MECHANICAL - INTERMEDIATE CWILLIAM Approved PER FINAL
06/01/2006 MECHANICAL - FINAL CWILLIAM Approved IVRS - Inspection :*
06/02/2006 PLUMBING - ROUGH, SOIL LHANLY Approved PER FINAL
06/02/2006 PLUMBING - FINAL LHANLY Approved IVRS - Inspection :*
CORRECTIONS FOR T.I MADE
06/02/2006 PLUMBING - PRE SLAB LHANLY Approved IVRS - Inspection :*
06/02/2006 BUILDING ABOVE CEILING LHANLY Approved IVRS - Inspection :*
06/02/2006 FIRE - FINAL LTHOMAS Approved
06/02/2006 FIRE SPKLR - FINAL LTHOMAS Approved
06/02/2006 PLUMBING - FINAL RMYERS Approved 1. CANNOT FINAL T.I UNTIL SHELL IS FINALED
2. T.I CORRECTIONS: C.P AND MACHINE SCREW ON CLEAN OUT SUPPORT CHICAGO FAUCET AT MOP SINK.
06/02/2006 FIRE SPKLR - FINAL RMYERS Approved IVRS - Inspection :*
06/08/2006 ELECTRIC - ABOVE CEILING CCLEMENS Approved PER FINAL
06/08/2006 BUILDING - FINAL LHANLY Approved IVRS - Inspection :*
06/08/2006 ELECTRIC - FINAL CCLEMENS Approved IVRS - Inspection :*
06/08/2006 ELECTRIC - CONSTRUCTION POWER CCLEMENS Approved IVRS - Inspection :*
06/08/2006 ELECTRIC - INTERMEDIATE CCLEMENS Approved IVRS - Inspection :*
06/13/2006 PERMIT FINALED AKLAPPER Approved
06/13/2006 SIGN - FINAL RHOLLAND Approved

Documents

File Name Document Type  
COFO_06-13-2006.TIF CERT OF OCC VIEW
None DOCUMENTS VIEW