Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address NEW:
270 S WILLIAMS BL
Apply Date:
12/01/2005
Applicant:
TRIUMPH BUILDERS SOUTHWEST LLC *C*
Description:
PARKING GARAGE
Contractors:
  • TRIUMPH BUILDERS SOUTHWEST LLC *C*

Permit Reviews

Permit Number - T05CM05978
Permit Status: C of o
Permit Description: PARKING GARAGE
Start Date Submittal Complete Date Status  
02/24/2006 3RD PARTY REVIEW-REVISION/OTHER 03/01/2006 COMPLETED Review Details
02/28/2006 POST 3RD PARTY REVIEW 03/01/2006 COMPLETED Review Details
12/09/2005 3RD PARTY REVIEW-REVISION/OTHER 12/14/2005 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T05CM05978
Permit Status: C of o
Permit Description: PARKING GARAGE
Total Outstanding Activity Conditions - 1
Date Name
12/01/2005 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T05CM05978
Permit Description: PARKING GARAGE
Total Completed Inspections - 18
Date Description Inspector Results Comments
12/15/2005 STEM WALL/RETAINING WALL LHANLY Approved IVRS - Inspection :*1ST LEVEL PRE CAST CONNECTS AT FOOTINGS OK
OUTSIDE RAMP WLL WEST & NORTH TO 25' FROM END.
INSIDE RAMP WALL OK FOR 1ST 20' FROM GARAGE
HIGH CAMP WALL SOUTH END TO GARAGE OK ( LINE ZZ)
12/15/2005 EXCAVATION/LAYOUT REBAR & ZON LHANLY Approved IVRS - Inspection :*
12/16/2005 BUILDING PRE-SLAB LHANLY Approved OK TO BACKFILL AND PAVE 1ST LEVEL ( GROUND LEVEL)
08/15/2006 PLUMBING - ROOF DRAINS RRICH Approved IVRS - Inspection :*
WATER TEST 10" RAIN DRAIN OK
08/15/2006 FRAMING GDABBS Approved IVRS - Inspection :*
08/15/2006 SIGN - FINAL JYBARRA Approved IVRS - Inspection :*
08/15/2006 FIRE - FINAL LTHOMAS Approved
08/15/2006 RIGHT OF WAY - FINAL NBRIGGS Approved PER EMAIL
08/16/2006 PLUMBING - FINAL RRICH Approved
08/17/2006 BUILDING - FINAL GDABBS Approved IVRS - Inspection :*
PENDING ELECTRICAL FINAL
08/18/2006 OUTDOOR LIGHTING FINAL RSUBA Approved IVRS - Inspection :*
08/18/2006 ELECTRIC - FINAL RSUBA Approved IVRS - Inspection :*
08/21/2006 ELECTRIC - INTERMEDIATE RSUBA Approved
08/21/2006 ELECTRIC - OUTDOOR LIGHTING RSUBA Approved
09/14/2006 NPPO - FINAL ACONNOR Approved
09/14/2006 LANDSCAPE - FINAL ACONNOR Approved
09/15/2006 ENGINEERING - FINAL NKALAHAR Approved ALL PUNCHLIST ITEMS HAVE BEEN ADDRESSED
09/18/2006 PERMIT FINALED DROBEY Approved