Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
Permit Number - T05CM05978
Inspection Description - ENGINEERING - FINAL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/15/2006 | ENGINEERING - FINAL | Approved | ALL PUNCHLIST ITEMS HAVE BEEN ADDRESSED | |
08/18/2006 | ENGINEERING - FINAL | Partial Approval | CP-Complete all paving 99%-Complete all striping ONGOING-Complete all Rip-Rap work CP-Complete all curbing work in parking area EAST BASIN CP NORTH BASIN WILL BE COMPLETED WITH LANDSCAPING-Re-establish grade at weir locations for both basins RCVD-Stamped basin certification letters from engineer need to be received ONGOING-Clean up all construction debris IN SW CORNER W/ BARRICADES/CAUTION TAPE-Remove all roll-off dumpsters and porta-toilets AFTER LANDSCAPING CP-Sweep Williams Blvd |
|
08/15/2006 | ENGINEERING - FINAL | Not ready for Inspection | T05BU00955 T05CM02515/T05CM05978 250 E. Williams Blvd PRELIMINARY PUNCHLIST ONLY -Complete all paving -Complete all striping -Complete all Rip-Rap work -Complete all curbing work in parking area -Re-establish grade at weir locations for both basins -Stamped basin certification letters from engineer need to be received -Clean up all construction debris -Remove all roll-off dumpsters and porta-toilets -Sweep Williams Blvd |