Permit: T05CM05707
Permit Details
Apply Date:
11/14/2005
Applicant:
N/A
Description:
TI: RETAIL
Contractors:
- M C CONSTRUCTION MANAGEMENT INC
Outstanding Activity Conditions
Permit Number - T05CM05707
Permit Status: C of o
Permit Description: TI: RETAIL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/14/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T05CM05707
Permit Description: TI: RETAIL
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/15/2006 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* PRE POUR OK OK FOR CONCRETE |
| 03/15/2006 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* 1. WILL REQUIRE STAMPED LETTER FROM ARCHITECT ALLOWING ABS IN LIEU OF PVC 2. NOT INSTALLED PER PLAN REDLINES ON SITE NO ENGINEERING REQ'D OK TO COVER 3. NEED TO SEE PRE POUR |
| 03/24/2006 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
| 04/03/2006 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* OK TO COVER ALL AREAS |
| 04/07/2006 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | IVRS - Inspection :* 1) HANGERS TO BE INSTALLED ACCORDING TO TABLE 3-1 94 UPC AND THE INSTALLATION STANDARD FOR BLACK IRON PIPE 2) BLACK IRON PIPE TO BE WRAPPED THRU EXTERIOR WALL 3) PRESSURE TEST FOR WATER HEATER OK |
| 04/12/2006 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 04/12/2006 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 05/15/2006 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection :* |
| 05/15/2006 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | IVRS - Inspection :* |
| 05/17/2006 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 05/18/2006 | RIGHT OF WAY - FINAL | MOTERO | Approved | PER EMAIL |
| 05/18/2006 | FIRE - FINAL | LLAKEY | Approved | |
| 05/18/2006 | FIRE SPKLR - FINAL | LLAKEY | Approved | |
| 05/23/2006 | PLUMBING - GAS PRESS TEST FNL | RMYERS | Approved | IVRS - Inspection :* |
| 05/25/2006 | SIGN - FINAL | JSONKIN | Approved | |
| 05/26/2006 | PERMIT FINALED | LJACKSON | Approved | |
| 05/26/2006 | OUTDOOR LIGHTING FINAL | CCLEMENS | Approved | |
| 05/26/2006 | ELECTRIC - FINAL | CCLEMENS | Approved | |
| 05/26/2006 | ELECTRIC - OUTDOOR LIGHTING | CCLEMENS | Approved | |
| 05/26/2006 | ELECTRIC - INTERMEDIATE | CCLEMENS | Approved | |
| 05/26/2006 | PLUMBING - FINAL | RMYERS | Approved | |
| 05/26/2006 | PLUMBING - PROGRESS | RMYERS | Approved | |
| 05/26/2006 | SITE - SEWER | RMYERS | Approved | |
| 05/26/2006 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | |
| 05/26/2006 | PLUMBING - ABOVE CEILING | RMYERS | Approved | |
| 05/26/2006 | BUILDING - FINAL | LHANLY | Approved | IVRS - Inspection :* |
| 05/26/2006 | ROOF NAILING | LHANLY | Approved | IVRS - Inspection :* |