Permit: T05CM05355
Permit Details
Apply Date:
10/20/2005
Applicant:
WSM ARCHITECTS/ JOEL MESIK
Description:
TI: SCHOOL
Architects:
- MICKELBERG, PAUL DAVID
Contractors:
- WISE CHOICE BUILDERS INC
Permit Reviews
Permit Number - T05CM05355
Permit Status: C of o
Permit Description: TI: SCHOOL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/21/2006 | POST 3RD PARTY REVIEW | 09/20/2006 | COMPLETED |
| 10/20/2005 | PLANS OK TO SUBMIT - 3RD PARTY | 10/25/2005 | COMPLETED |
| 10/20/2005 | PLANS OK TO SUBMIT - SITE | 10/20/2005 | COMPLETED |
| 10/25/2005 | 3RD PARTY REVIEW-COMMERCIAL TI | 02/21/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM05355
Permit Status: C of o
Permit Description: TI: SCHOOL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/20/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T05CM05355
Permit Description: TI: SCHOOL
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/30/2007 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* OK TO COVER UNDERGROUND |
| 01/30/2007 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* |
| 05/29/2007 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
| 05/30/2007 | MECHANICAL - ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 05/31/2007 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
| 06/05/2007 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 06/05/2007 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 06/26/2007 | ELECTRIC - ABOVE CEILING | CCLEMENS | Approved | IVRS - Inspection :* |
| 08/06/2007 | RIGHT OF WAY - FINAL | MOTERO | Approved | PER EMAIL |
| 08/06/2007 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* OK C OF O |
| 08/06/2007 | NPPO - FINAL | ACONNOR | Approved | N/A |
| 08/06/2007 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 08/07/2007 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 08/07/2007 | ELECTRIC - FINAL | CCLEMENS | Approved | IVRS - Inspection :* |
| 08/07/2007 | ELECTRIC - INTERMEDIATE | CCLEMENS | Approved | IVRS - Inspection :* |
| 08/07/2007 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
| 08/07/2007 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* |
| 08/07/2007 | FIRE - FINAL | LTHOMAS | Approved | |
| 08/07/2007 | FIRE - ALARM FINAL | LTHOMAS | Approved | |
| 08/07/2007 | ENGINEERING - FINAL | MRUSSO | Approved | EXISTING DRAINAGE PARKING LOT DRAINAGE PROBLEMS WILL BE ADDRESSED UNDER A FUTURE TI PER CONVERSATION WITH SUPER (WISE CHOICE BLDRS) . WORK HAS BEEN COMPLETED PER THE APPROVED SITE PLAN. |
| 08/08/2007 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | |
| 08/08/2007 | PERMIT FINALED | BFLORES | Approved |