Permit: T05CM05178
Permit Details
Apply Date:
10/12/2005
Applicant:
RANDEL JACOB DESIGN GROUP, LANA MOUSSA
Description:
NEW OFFICE
Contractors:
- CLAVOS BUILDING COMPANY L L C
Permit Reviews
Permit Number - T05CM05178
Permit Status: Withdrwn
Permit Description: NEW OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/22/2007 | RESUBMITTAL | 03/02/2007 | COMPLETED |
| 03/01/2007 | SITE | 03/06/2007 | ACTIVE |
| 03/02/2007 | RESUBMITTAL | 03/06/2007 | ACTIVE |
| 10/12/2005 | PLANS OK TO SUBMIT - 3RD PARTY | 12/23/2005 | COMPLETED |
| 12/14/2006 | POST 3RD PARTY REVIEW | 02/22/2007 | COMPLETED |
| 12/23/2005 | 3RD PARTY REVIEW-COMMERCIAL | 12/14/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM05178
Permit Status: Withdrwn
Permit Description: NEW OFFICE
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 10/12/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 12/14/2006 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
Outstanding Inspections
Permit Status: Withdrwn
Permit Number: T05CM05178
Permite Description: NEW OFFICE
Total Outstanding Inspections - 22
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| EXCAVATION/LAYOUT REBAR & ZON | N/A | Not Inspected | ||
| STEM WALL/RETAINING WALL | N/A | Not Inspected | ||
| BUILDING PRE-SLAB | N/A | Not Inspected | ||
| REINFORCED MASONRY PRE-GROUT | N/A | Not Inspected | ||
| ROOF NAILING | N/A | Not Inspected | ||
| FRAMING | N/A | Not Inspected | ||
| U VALUE FOR WINDOW | N/A | Not Inspected | ||
| SHEET ROCK NAILING | N/A | Not Inspected | ||
| BUILDING - PROGRESS | N/A | Not Inspected | ||
| BUILDING - FINAL | N/A | Not Inspected | ||
| ELECTRIC - UFER | N/A | Not Inspected | ||
| ELECTRIC - INTERMEDIATE | N/A | Not Inspected | ||
| ELECTRIC - OUTDOOR LIGHTING | N/A | Not Inspected | ||
| ELECTRIC - FINAL | N/A | Not Inspected | ||
| OUTDOOR LIGHTING FINAL | N/A | Not Inspected | ||
| PLUMBING - ROUGH, SOIL | N/A | Not Inspected | ||
| PLUMBING - INTERMEDIATE | N/A | Not Inspected | ||
| PLUMBING - SEWER HCS CONNECT | N/A | Not Inspected | ||
| PLUMBING - PROGRESS | N/A | Not Inspected | ||
| PLUMBING - FINAL | N/A | Not Inspected | ||
| MECHANICAL - INTERMEDIATE | N/A | Not Inspected | ||
| MECHANICAL - FINAL | N/A | Not Inspected |