Permit: T05CM03614
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
7474 E BROADWAY BL #150
Address NEW:
7474 E BROADWAY BL #150
Apply Date:
07/11/2005
Applicant:
N/A
Description:
TI: VET
Contractors:
- GILES CONSTRUCTION INC
Permit Reviews
Permit Number - T05CM03614
Permit Status: C of o
Permit Description: TI: VET
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/04/2006 | 3RD PARTY REVIEW-REVISION/OTHER | 01/04/2006 | COMPLETED |
| 07/11/2005 | PLANS OK TO SUBMIT - COMM | 07/11/2005 | COMPLETED |
| 07/11/2005 | 3RD PARTY REVIEW-COMMERCIAL TI | 09/08/2005 | COMPLETED |
| 09/08/2005 | POST 3RD PARTY REVIEW | 09/19/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM03614
Permit Status: C of o
Permit Description: TI: VET
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/11/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T05CM03614
Permit Description: TI: VET
Total Completed Inspections - 36
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/26/2005 | PLUMBING - ROUGH, SOIL | TRINIVJR | Approved | IVRS - Inspection :**DWV WATER TEST IS OK OK TO BACKFILL TRENCH |
| 12/29/2005 | ELECTRIC - UNDERGROUND | RSUBA | Approved | IVRS - Inspection :* |
| 12/30/2005 | EXCAVATION/LAYOUT REBAR & ZON | JCAGLE | Approved | IVRS - Inspection :* |
| 01/27/2006 | ROOF NAILING | JCAGLE | Approved | IVRS - Inspection :* |
| 01/31/2006 | EXT METAL CLIPS/EXT SHEATHING | JCAGLE | Approved | IVRS - Inspection :* |
| 02/08/2006 | REINFORCED MASONRY PRE-GROUT | JCAGLE | Approved | IVRS - Inspection :* I.C.U ROOMS #1, 2 (4'-10'4") |
| 02/09/2006 | STEM WALL/RETAINING WALL | JCAGLE | Approved | IVRS - Inspection :* |
| 02/14/2006 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* 1) AIR TEST WASTE AND VENT TO JUST PRIOR TO THRU ROOF OK IN BLOCK AREAS. WATER PIPING IS OK |
| 02/14/2006 | ELECTRIC - INTERMEDIATE | RSUBA | Approved | IVRS - Inspection :* |
| 03/03/2006 | FRAMING | JCAGLE | Approved | IVRS - Inspection :* FURROUTS DONE |
| 03/11/2006 | STUCCO MESH | JCAGLE | Approved | IVRS - Inspection :* REMAINDER OF BUILDING OK |
| 03/17/2006 | ELECTRIC - SERVICE RELOCATION | RSUBA | Approved | IVRS - Inspection :* NO CLEARANCE REQ'D AT THIS TIME |
| 03/27/2006 | PLUMBING - MEDICAL GAS/TEST | RMYERS | Approved | IVRS - Inspection :* 1. TESTER/VERIFIER APPROVED INTERMEDIATE TESTS. 2. OK TO COVER. |
| 04/07/2006 | ELECTRIC - UFER | RSUBA | Approved | IVRS - Inspection :* |
| 04/11/2006 | SHEET ROCK NAILING | JCAGLE | Approved | IVRS - Inspection :* |
| 04/11/2006 | RIGHT OF WAY - FINAL | NBRIGGS | Approved | PER EMAIL |
| 04/13/2006 | ENGINEERING - FINAL | NKALAHAR | Approved | DISCUSSED WITH JASON CAGLE AND LEE RAY TRUNCATED DOMES ARE TO BE INSTALLED AT ACCESS RAMP 2' DEEP ALONG ENTIRE LENGTH OF LANDING (5') |
| 04/19/2006 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
| 04/27/2006 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* CONDENSORS #4,7,8 MUST USE 40 AMP. FUSES #9 NEEDS 20 AMP. FUSES FAN COIL DISCONNECTS IMPROPERLY FUSED. |
| 04/27/2006 | U VALUE FOR WINDOW | JCAGLE | Approved | IVRS - Inspection :* |
| 04/27/2006 | ELECTRIC - OUTDOOR LIGHTING | RSUBA | Approved | IVRS - Inspection :* |
| 05/02/2006 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* OK FOR FINAL C OF O |
| 05/02/2006 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* TRUNCATED DOMES |
| 05/02/2006 | PLUMBING - PROGRESS | RRICH | Approved | IVRS - Inspection :* FINISH ALL PLUMBING FIXTURE WORK PROVIDE CORRECT BACKFLOW PROTECTION WHERE REQUIRED |
| 05/03/2006 | OUTDOOR LIGHTING FINAL | RSUBA | Approved | IVRS - Inspection :* |
| 05/03/2006 | ELECTRIC - FINAL | RSUBA | Approved | IVRS - Inspection :* |
| 05/03/2006 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 05/03/2006 | FIRE - FINAL | LTHOMAS | Approved | |
| 05/03/2006 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 05/03/2006 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
| 05/03/2006 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
| 05/03/2006 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 05/08/2006 | BUILDING - FINAL | RRICH | Approved | IVRS - Inspection :* |
| 05/08/2006 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
| 05/08/2006 | PLUMBING - MEDICAL GAS/FINAL | RRICH | Approved | IVRS - Inspection :* |
| 05/09/2006 | PERMIT FINALED | AKLAPPER | Approved |