Permit: T05CM02734
Permit Details
Apply Date:
06/14/2005
Applicant:
SALSA HOMES L L C ,
Description:
DUPLEX TD# 16-36-33
Contractors:
- SALSA HOMES L L C ,
Outstanding Activity Conditions
Permit Number - T05CM02734
Permit Status: Final
Permit Description: DUPLEX TD# 16-36-33
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/14/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T05CM02734
Permit Description: DUPLEX TD# 16-36-33
Total Completed Inspections - 26
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/12/2005 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* 1) ABS DWV UNDERGROUND OK-CONTRACTOR TO REDLINE INSTALLATION-PLAN VAGUE AND INCOMPLETE 2) AIR TEST OK 3) OK TO COVER |
| 07/13/2005 | BUILDING PRE-SLAB | AMATHIES | Approved | IVRS - Inspection :* |
| 07/13/2005 | EXCAVATION/LAYOUT REBAR & ZON | AMATHIES | Approved | IVRS - Inspection :* |
| 07/13/2005 | ELECTRIC - UFER | RMAJUTA | Approved | IVRS - Inspection :* |
| 09/09/2005 | EXT METAL CLIPS/EXT SHEATHING | AMATHIES | Approved | IVRS - Inspection :* 1) NAIL HOLDOWNS |
| 09/09/2005 | ROOF NAILING | AMATHIES | Approved | IVRS - Inspection :* |
| 10/14/2005 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :*OK WALLS & CEILINGS-FEEDERS TO BE COPPER PER PLAN |
| 10/17/2005 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | IVRS - Inspection :* |
| 10/23/2005 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :*JOINT SEWER AGREEMENT TO BE STAMPED BY COUNTY RECORDER. YARDWATER OK OK TO COVER WALLS AND CEILING |
| 10/23/2005 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :* |
| 10/23/2005 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection :* |
| 10/24/2005 | U VALUE FOR WINDOW | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/26/2005 | STUCCO MESH | AQUIROZ | Approved | IVRS - Inspection :* |
| 11/04/2005 | SHEET ROCK NAILING | AMATHIES | Approved | IVRS - Inspection :* |
| 11/04/2005 | FRAMING | AMATHIES | Approved | IVRS - Inspection :* |
| 01/19/2006 | ELECTRIC - CABLE DROP | CCLEMENS | Approved | IVRS - Inspection :* |
| 01/19/2006 | ELECTRIC - UNDERGROUND | CCLEMENS | Approved | IVRS - Inspection :* |
| 01/20/2006 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :*NO BACKWATER VALVE SEWER /HCS APPROVED ON 10/23/05 PLUMBING FINAL OK OK FOR C OF O PENDING ANY OTHER INSPECTIONS. |
| 01/20/2006 | TEP CLEARANCE - AM | JKOZUCH | Approved | ECO |
| 01/20/2006 | SITE - SEWER | RMYERS | Approved | IVRS - Inspection :* |
| 01/20/2006 | PLUMBING - BACK WATER VALVE | RMYERS | Approved | IVRS - Inspection :* |
| 02/15/2006 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection :* |
| 02/21/2006 | ELECTRIC - FINAL | CCLEMENS | Approved | IVRS - Inspection :* |
| 02/21/2006 | OUTDOOR LIGHTING FINAL | CCLEMENS | Approved | IVRS - Inspection :* |
| 02/21/2006 | ELECTRIC - OUTDOOR LIGHTING | CCLEMENS | Approved | IVRS - Inspection :* |
| 02/22/2006 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |