Permit: T05CM01332
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
9155 E TANQUE VERDE RD #157
Address NEW:
9155 E TANQUE VERDE RD #157
Apply Date:
03/24/2005
Applicant:
CARHUFF, PHILIP ANDREW
Description:
TI:NAIL SALON
Architects:
- CARHUFF, PHILIP ANDREW
Contractors:
- LYONS' SOUTHWEST CONSTRUCTION ,
Permit Reviews
Permit Number - T05CM01332
Permit Status: C of o
Permit Description: TI:NAIL SALON
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/24/2005 | COMMERCIAL TI | 04/18/2005 | COMPLETED |
| 04/18/2005 | REVISION | 04/21/2005 | COMPLETED |
| 05/05/2005 | REVISION - WALK THRU | 05/05/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM01332
Permit Status: C of o
Permit Description: TI:NAIL SALON
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/24/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T05CM01332
Permit Description: TI:NAIL SALON
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/15/2005 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* 1) SUPPORT M/C CABLE WITH ?? 12" OF BOXES. 2) WE HAVE CONDUCTOR OVER FILL AT BOX ABOVE CEILING 3) VDV CABLEING TO BE SUPPORTED OR A ABANDONED 725.2 & 725.6, 800.2, 800.6 4) IS THERE A LIGHTING PLAN? OK WALLS |
| 05/04/2005 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 05/04/2005 | FRAMING | BSTEVENS | Approved | IVRS - Inspection :* PENDING PLB INT. APPROVAL |
| 05/06/2005 | SIGN - FINAL | RDEAR | Approved | |
| 05/09/2005 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
| 05/09/2005 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* |
| 05/09/2005 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* |
| 05/09/2005 | TEP CLEARANCE - AM | JKOZUCH | Approved | INC |
| 05/11/2005 | SHEET ROCK NAILING | BSTEVENS | Approved | IVRS - Inspection :* |
| 05/24/2005 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* 1) OK FOR C OF O |
| 05/24/2005 | PLUMBING - PROGRESS | RRICH | Approved | IVRS - Inspection :* 1) CLOSET FLANGE OK |
| 05/24/2005 | FIRE - FINAL | LTHOMAS | Approved | |
| 05/24/2005 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 05/24/2005 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* |
| 05/27/2005 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* 1) 8 BACKFLOW CERTIFICATION FOR (4) FOOT SPA'S TURNED IN |
| 05/27/2005 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* / OK FINAL |
| 05/31/2005 | BUILDING - FINAL | BSTEVENS | Approved | IVRS - Inspection :* |
| 06/01/2005 | PERMIT FINALED | JMORALES | Approved | |
| 06/01/2005 | ENGINEERING - FINAL | JSALINE | Approved |