Permit: T05CM00490
Permit Details
Apply Date:
02/04/2005
Applicant:
DELGADO BENNY & GEORGINA CP/RS
Description:
DUPLEX:NEW
Contractors:
- IGUANA CONSTRUCTION CO INC ,
Outstanding Activity Conditions
Permit Number - T05CM00490
Permit Status: Final
Permit Description: DUPLEX:NEW
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/04/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T05CM00490
Permit Description: DUPLEX:NEW
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/02/2005 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :*APPROVED |
| 05/02/2005 | EXCAVATION/LAYOUT REBAR & ZON | AMATHIES | Approved | IVRS - Inspection :* |
| 05/16/2005 | STEM WALL/RETAINING WALL | AMATHIES | Approved | IVRS - Inspection :* |
| 06/01/2005 | PLUMBING - YARD WTR LINE/TEST | TRINIVJR | Approved | IVRS - Inspection :* |
| 06/01/2005 | PLUMBING - ROUGH, SOIL | TRINIVJR | Approved | IVRS - Inspection :* |
| 06/03/2005 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection :* / 1) HCS CONNECTION OK. OK TO COVER |
| 07/11/2005 | REINFORCED MASONRY PRE-GROUT | HLEYVA | Approved | IVRS - Inspection :* |
| 08/22/2005 | ROOF NAILING | AMATHIES | Approved | IVRS - Inspection :* |
| 09/01/2005 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection :* |
| 09/02/2005 | TEP CLEARANCE - AM | FGREER | Approved | CEC ON (2) AND ECO ON (1) CLEARED BY DAN |
| 09/07/2005 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* 1) CORRECTION MADE |
| 09/09/2005 | FRAMING | AMATHIES | Approved | IVRS - Inspection :* |
| 09/09/2005 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | IVRS - Inspection :* |
| 09/26/2005 | SHEET ROCK NAILING | AMATHIES | Approved | IVRS - Inspection :* |
| 09/26/2005 | U VALUE FOR WINDOW | AMATHIES | Approved | IVRS - Inspection :* |
| 11/01/2005 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection :* |
| 11/14/2005 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 11/17/2005 | ELECTRIC - TEMPORARY SERVICE | DSANTACR | Approved | |
| 11/17/2005 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
| 11/17/2005 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 11/21/2005 | BUILDING PRE-SLAB | AMATHIES | Approved | |
| 11/21/2005 | BUILDING - FINAL | AMATHIES | Approved | |
| 05/23/2006 | PERMIT FINALED | LJACKSON | Approved |