Permit: T05CM00155
Permit Details
Apply Date:
01/12/2005
Applicant:
RODRIGUEZ INC , C E
Description:
ADDITION:BEDROOM/BATHROOM/KITCHEN
Contractors:
- RODRIGUEZ INC , C E
Permit Reviews
Permit Number - T05CM00155
Permit Status: Final
Permit Description: ADDITION:BEDROOM/BATHROOM/KITCHEN
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/12/2005 | PLANS OK TO SUBMIT - SITE | 01/19/2005 | COMPLETED |
| 01/21/2005 | 3RD PARTY REVIEW-RESIDENTIAL | 03/11/2005 | COMPLETED |
| 03/11/2005 | POST 3RD PARTY REVIEW | 03/30/2005 | COMPLETED |
| 03/31/2005 | RESUBMITTAL | 04/04/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM00155
Permit Status: Final
Permit Description: ADDITION:BEDROOM/BATHROOM/KITCHEN
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/12/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T05CM00155
Permit Description: ADDITION:BEDROOM/BATHROOM/KITCHEN
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/07/2005 | ELECTRIC - UFER | RFREIDIN | Approved | |
| 04/07/2005 | EXCAVATION/LAYOUT REBAR & ZON | RFREIDIN | Approved | IVRS - Inspection :* |
| 04/07/2005 | PLUMBING - ROUGH, SOIL | RFREIDIN | Approved | IVRS - Inspection :* |
| 04/12/2005 | BUILDING PRE-SLAB | DQUINN | Approved | IVRS - Inspection :* |
| 11/21/2005 | ROOF NAILING | WNORTH | Approved | IVRS - Inspection :* |
| 11/21/2005 | EXT METAL CLIPS/EXT SHEATHING | WNORTH | Approved | IVRS - Inspection :* |
| 12/06/2007 | U VALUE FOR WINDOW | DQUINN | Approved | IVRS - Inspection :* |
| 12/12/2007 | STUCCO MESH | DQUINN | Approved | IVRS - Inspection :* |
| 03/19/2008 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | IVRS - Inspection :* |
| 03/19/2008 | FRAMING | DQUINN | Approved | IVRS - Inspection :* |
| 03/19/2008 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 03/19/2008 | PLUMBING - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 03/19/2008 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 03/26/2008 | SHEET ROCK NAILING | DQUINN | Approved | IVRS - Inspection :* |
| 11/14/2008 | REINFORCED MASONRY PRE-GROUT | DQUINN | Approved | IVRS - Inspection :* |
| 11/14/2008 | MECHANICAL - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 11/14/2008 | PLUMBING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 11/14/2008 | ELECTRIC - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 11/14/2008 | BUILDING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 11/17/2008 | PERMIT FINALED | JWEATHER | Approved |