Permit: T04CM05006
Permit Details
Apply Date:
11/12/2004
Applicant:
J R TUTTLE CO
Description:
AUTO SHOP W/OFFICE:NEW
Contractors:
- J R TUTTLE CO
Permit Reviews
Permit Number - T04CM05006
Permit Status: C of o
Permit Description: AUTO SHOP W/OFFICE:NEW
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/07/2005 | POST 3RD PARTY REVIEW | 02/03/2005 | COMPLETED |
01/24/2005 | SITE | 03/18/2005 | COMPLETED |
02/03/2005 | RESUBMITTAL | 03/18/2005 | COMPLETED |
11/12/2004 | PLANS OK TO SUBMIT - 3RD PARTY | 11/12/2004 | COMPLETED |
11/12/2004 | 3RD PARTY REVIEW-COMMERCIAL | 01/07/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T04CM05006
Permit Status: C of o
Permit Description: AUTO SHOP W/OFFICE:NEW
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
11/12/2004 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T04CM05006
Permit Description: AUTO SHOP W/OFFICE:NEW
Total Completed Inspections - 40
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/08/2005 | NPPO PRE PERMIT INSPECTION | ACONNOR | Approved | |
02/17/2005 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | IVRS - Inspection :* |
03/10/2005 | BUILDING PRE-SLAB | LHANLY | Approved | IVRS - Inspection :*APPROVED |
03/10/2005 | STEM WALL/RETAINING WALL | LHANLY | Approved | IVRS - Inspection :* |
03/25/2005 | FRAMING | LHANLY | Approved | IVRS - Inspection :* |
03/25/2005 | EXT METAL CLIPS/EXT SHEATHING | LHANLY | Approved | IVRS - Inspection :* |
03/25/2005 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :*APPROVED |
03/29/2005 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* WATER TEST WASTE & VENT THRU ROOF OK |
03/31/2005 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* H20 PIPING IN WALL * OVERHEAD OK. 100PSI AIR TEST ON AIR PIPING OK STUBBED PER PLAN |
04/05/2005 | ELECTRIC - INTERMEDIATE | RSUBA | Approved | IVRS - Inspection :* |
04/06/2005 | ELECTRIC - UNDERGROUND | RSUBA | Approved | 4" SECONDARY OK TO COVER |
04/14/2005 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
04/14/2005 | REINFORCED MASONRY PRE-GROUT | LHANLY | Approved | IVRS - Inspection :* |
04/14/2005 | BUILDING ABOVE CEILING | LHANLY | Approved | IVRS - Inspection :* |
05/24/2005 | ELECTRIC - CABLE DROP | RMAJUTA | Approved | IVRS - Inspection :* |
05/24/2005 | ELECTRIC - ABOVE CEILING | RMAJUTA | Approved | IVRS - Inspection :* |
05/24/2005 | ELECTRIC - UFER | RMAJUTA | Approved | IVRS - Inspection :* |
05/27/2005 | ELECTRIC - TEMP POWER FOR TEST | RHOLLAND | Approved | IVRS - Inspection :* 1) OK TEMP POWER FOR TEST PER RAY MAJUTA |
05/27/2005 | TEP CLEARANCE - PM | SLONG | Approved | ECO |
06/01/2005 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* OK FOR CEILING TILES |
06/01/2005 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
06/06/2005 | FIRE - FINAL | LTHOMAS | Approved | |
06/06/2005 | NPPO - FINAL | ACONNOR | Approved | |
06/06/2005 | LANDSCAPE - FINAL | ACONNOR | Approved | |
06/06/2005 | U VALUE FOR WINDOW | LHANLY | Approved | IVRS - Inspection :* |
06/06/2005 | SHEET ROCK NAILING | LHANLY | Approved | IVRS - Inspection :* |
06/06/2005 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
06/07/2005 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* OK FOR FINAL C OF O |
06/07/2005 | OUTDOOR LIGHTING FINAL | RMAJUTA | Approved | IVRS - Inspection :* |
06/08/2005 | PLUMBING - SEWER HCS CONNECT | LHANLY | Approved | |
06/08/2005 | BUILDING - FINAL | LHANLY | Approved | IVRS - Inspection :* |
06/08/2005 | PLUMBING - FINAL | LHANLY | Approved | IVRS - Inspection :* |
06/08/2005 | ELECTRIC - FINAL | LHANLY | Approved | IVRS - Inspection :* |
06/08/2005 | BUILDING - FINAL | LHANLY | Approved | IVRS - Inspection :* |
06/08/2005 | ROOF NAILING | LHANLY | Approved | IVRS - Inspection :* |
06/08/2005 | PLUMBING - FINAL | TRINIVJR | Approved | IVRS - Inspection :* 1) CANNOT HAVE A FLEX LINE IN THE T & P DRAIN. SHALL PROVIDE A FULL SIZE DRAIN. 2) OK FOR TEMP C OF O AS PER STEVE LONG |
06/10/2005 | RIGHT OF WAY - FINAL | DLEE | Approved | PER EMAIL |
06/10/2005 | RIGHT OF WAY - FINAL | DLEE | Approved | APPROVED PER D LEE |
06/14/2005 | PERMIT FINALED | LJACKSON | Approved | |
06/14/2005 | ENGINEERING - FINAL | JSALINE | Approved | PER INSP FORM |