Permit: T04CM04919
Permit Details
Apply Date:
11/09/2004
Applicant:
CARRERA CUSTOM HOMES INC ,
Description:
DUPLEX TD#15-10-66
Contractors:
- CARRERA CUSTOM HOMES INC ,
Outstanding Activity Conditions
Permit Number - T04CM04919
Permit Status: Final
Permit Description: DUPLEX TD#15-10-66
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/09/2004 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T04CM04919
Permit Description: DUPLEX TD#15-10-66
Total Completed Inspections - 26
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/28/2004 | PLUMBING - ROUGH, SOIL | ROHAVER | Approved | |
| 10/01/2004 | ELECTRIC - UFER | RMAJUTA | Approved | |
| 10/01/2004 | EXCAVATION/LAYOUT REBAR & ZON | AMATHIES | Approved | |
| 10/01/2004 | BUILDING PRE-SLAB | AMATHIES | Approved | |
| 10/18/2004 | EXT METAL CLIPS/EXT SHEATHING | AQUIROZ | Approved | |
| 10/21/2004 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | |
| 10/26/2004 | PLUMBING - INTERMEDIATE | RMYERS | Approved | 1)ABS DWV THRU ROOF, PWX OK 2) CLOSET FLANGES OK 3) TUBS OK 4) REMEMBER HARIZ. X HORIZ. CHANGE OF DIRECTION TO BE A SWEEP |
| 10/27/2004 | U VALUE FOR WINDOW | AQUIROZ | Approved | |
| 11/02/2004 | STUCCO MESH | AQUIROZ | Approved | |
| 11/03/2004 | FRAMING | AQUIROZ | Approved | |
| 11/10/2004 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 11/15/2004 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 12/13/2004 | ELECTRIC - CABLE DROP | MCAPISTR | Approved | IVRS - Inspection :* |
| 12/14/2004 | TEP CLEARANCE - AM | RMAJUTA | Approved | cable drop only |
| 12/20/2004 | ELECTRIC - TEMPORARY SERVICE | MCAPISTR | Approved | IVRS - Inspection :* |
| 12/23/2004 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection :*/1)SEWER/HCS CONNECTION OK. WATER TEST OK. OK TO COVER |
| 12/23/2004 | ELECTRIC - FINAL | MCAPISTR | Approved | IVRS - Inspection :* |
| 12/23/2004 | ELECTRIC - UNDERGROUND | MCAPISTR | Approved | IVRS - Inspection :* |
| 12/23/2004 | ELECTRIC - INTERMEDIATE | MCAPISTR | Approved | IVRS - Inspection :* |
| 12/28/2004 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection :* |
| 01/13/2005 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :*APPROVED |
| 01/24/2005 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* 1) PLUMBING FINAL OK. OK FOR C OF O PENDING ANY OTHER INSPECTION. |
| 01/24/2005 | PLUMBING - GAS PRESS TEST FNL | RMYERS | Approved | IVRS - Inspection :* PRESSURE TEST APP. |
| 01/24/2005 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | IVRS - Inspection :* GAS PRESSURE TEST OK APP |
| 01/26/2005 | BUILDING - FINAL | AMATHIES | Approved | IVRS - Inspection :* |
| 08/02/2005 | PERMIT FINALED | AMATHIES | Approved |