Permit: T04CM00834
Permit Details
Apply Date:
02/24/2004
Applicant:
METRO PERMIT EXPRESS, INC
Description:
NEW:OFFICE BUILDING
Architects:
- EGLIN, EVAN SAR
Contractors:
- VENTURE WEST INC
Permit Reviews
Permit Number - T04CM00834
Permit Status: C of o
Permit Description: NEW:OFFICE BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/24/2004 | PLANS OK TO SUBMIT - 3RD PARTY | 02/25/2004 | COMPLETED |
| 02/25/2004 | 3RD PARTY REVIEW-COMMERCIAL | 03/11/2004 | COMPLETED |
| 02/25/2004 | 3RD PARTY REVIEW-COMMERCIAL | 03/26/2004 | COMPLETED |
| 03/29/2004 | 3RD PARTY REVIEW-COMMERCIAL | 04/06/2004 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T04CM00834
Permit Status: C of o
Permit Description: NEW:OFFICE BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/24/2004 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T04CM00834
Permit Description: NEW:OFFICE BUILDING
Total Completed Inspections - 38
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/07/2004 | PLUMBING - SEWER HCS CONNECT | JSTANLEY | Approved | IVRS - Inspection 0000* |
| 04/07/2004 | PLUMBING - ROUGH, SOIL | JSTANLEY | Approved | IVRS - Inspection 0000* |
| 04/21/2004 | ELECTRIC - UFER | RHOLLAND | Approved | IVRS - Inspection 0000*/ OK 2 X 3/0 TO REBAR. |
| 04/21/2004 | BUILDING PRE-SLAB | RSUBA | Approved | IVRS - Inspection 0000* |
| 04/21/2004 | EXCAVATION/LAYOUT REBAR & ZON | RSUBA | Approved | IVRS - Inspection 0000* |
| 06/07/2004 | ROOF NAILING | RSUBA | Approved | IVRS - Inspection :* |
| 06/07/2004 | EXT METAL CLIPS/EXT SHEATHING | RSUBA | Approved | IVRS - Inspection :* |
| 06/22/2004 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :*/ OK WALLS. |
| 07/21/2004 | SHEET ROCK NAILING | AMATHIES | Approved | IVRS - Inspection :* |
| 07/21/2004 | STUCCO MESH | AMATHIES | Approved | IVRS - Inspection :* |
| 07/30/2004 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* |
| 08/03/2004 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | SUSPENDED ROUGH DUCTS - SUPPLY/RETURN DOWN THRU ROOF |
| 08/05/2004 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :*/ 1) OK FOR CEILING TILES |
| 08/10/2004 | PLUMBING - TEMP POWER FOR TEST | JSTANLEY | Approved | |
| 08/10/2004 | ELECTRIC - TEMP POWER FOR TEST | RHOLLAND | Approved | |
| 08/10/2004 | PLUMBING - TEMP POWER FOR TEST | TRINIVJR | Approved | IVRS - Inspection : See detailed listing on site.| 999*/ 1) SHALL HAVE INTERMEDIATE INSPECTION COMPLETED PRIOR TO TEMP POWER RELEASE |
| 08/13/2004 | ELECTRIC - TEMPORARY SERVICE | RHOLLAND | Approved | IVRS - Inspection :* |
| 08/16/2004 | TEP CLEARANCE - AM | JKOZUCH | Approved | |
| 08/24/2004 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :*/ 1) OK FOR FINAL C OF O |
| 08/24/2004 | FIRE - FINAL | LTHOMAS | Approved | 1) OK C OF O |
| 08/24/2004 | OUTDOOR LIGHTING FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
| 08/24/2004 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 08/24/2004 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | |
| 08/26/2004 | ELECTRIC - UNDERGROUND | RMAJUTA | Approved | |
| 08/26/2004 | ELECTRIC - CABLE DROP | RMAJUTA | Approved | |
| 08/26/2004 | ENGINEERING - FINAL | JSALINE | Approved | C OF O APPROVED. 1. REQUESTED PUNCH LIST ITEMS WERE ADDRESSED. |
| 08/26/2004 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 08/26/2004 | NPPO - FINAL | ACONNOR | Approved | |
| 08/26/2004 | ELECTRIC - FINAL | RMAJUTA | Approved | IVRS - Inspection :* |
| 08/27/2004 | PERMIT FINALED | TACHONG | Approved | |
| 08/27/2004 | PLUMBING - INTERMEDIATE | JSTANLEY | Approved | |
| 08/27/2004 | PLUMBING - ROOF DRAINS | JSTANLEY | Approved | |
| 08/27/2004 | PLUMBING - YARD WTR LINE/TEST | JSTANLEY | Approved | |
| 08/27/2004 | BUILDING - FINAL | RSUBA | Approved | |
| 08/27/2004 | U VALUE FOR WINDOW | RSUBA | Approved | |
| 08/27/2004 | FRAMING | RSUBA | Approved | |
| 08/27/2004 | STEM WALL/RETAINING WALL | RSUBA | Approved | |
| 08/27/2004 | PLUMBING - FINAL | JSTANLEY | Approved | IVRS - Inspection :* |