Permit: T04CM00340
Permit Details
Status:
C of o
Type:
COMMERCIAL NEW
Address:
4810 E CAMP LOWELL DR
Address NEW:
4810 E CAMP LOWELL DR
Apply Date:
01/27/2004
Applicant:
METRO PERMIT EXPRESS, INC
Description:
NEW OFFICE BUILDING
Contractors:
- VENTURE WEST INC
Permit Reviews
Permit Number - T04CM00340
Permit Status: C of o
Permit Description: NEW OFFICE BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/27/2004 | PLANS OK TO SUBMIT - 3RD PARTY | 01/28/2004 | COMPLETED |
| 01/29/2004 | 3RD PARTY REVIEW-COMMERCIAL | 02/23/2004 | COMPLETED |
| 04/01/2004 | 3RD PARTY REVIEW-REVISION/OTHER | 04/15/2004 | COMPLETED |
| 04/15/2004 | 3RD PARTY REVIEW-REVISION/OTHER | 05/17/2004 | COMPLETED |
| 05/17/2004 | RESUBMITTAL | 06/07/2004 | COMPLETED |
| 06/03/2004 | POST 3RD PARTY REVIEW | 06/07/2004 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T04CM00340
Permit Description: NEW OFFICE BUILDING
Total Completed Inspections - 40
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/10/2004 | PLUMBING - SEWER HCS CONNECT | JSTANLEY | Approved | IVRS - Inspection 0000* |
| 03/10/2004 | PLUMBING - ROUGH, SOIL | JSTANLEY | Approved | IVRS - Inspection 0000* |
| 03/23/2004 | ELECTRIC - UFER | RHOLLAND | Approved | IVRS - Inspection 0000*/ 1) OK 3/0 TO REBAR |
| 03/23/2004 | BUILDING PRE-SLAB | RSUBA | Approved | IVRS - Inspection 0000* |
| 03/23/2004 | STEM WALL/RETAINING WALL | RSUBA | Approved | IVRS - Inspection 0000* |
| 03/23/2004 | EXCAVATION/LAYOUT REBAR & ZON | RSUBA | Approved | IVRS - Inspection 0000* |
| 04/26/2004 | EXT METAL CLIPS/EXT SHEATHING | AQUIROZ | Approved | IVRS - Inspection :* |
| 04/27/2004 | FRAMING | RSUBA | Approved | IVRS - Inspection : See detailed listing on site.| 999* |
| 04/27/2004 | ROOF NAILING | RSUBA | Approved | IVRS - Inspection : See detailed listing on site.| 999* |
| 04/30/2004 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :/ 1) OK WALLS AND HARD LIDS |
| 05/10/2004 | STUCCO MESH | RSUBA | Approved | IVRS - Inspection :* |
| 05/13/2004 | SHEET ROCK NAILING | HLEYVA | Approved | IVRS - Inspection :* |
| 05/28/2004 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :*/ OK TO TILE. |
| 06/01/2004 | MECHANICAL - ABOVE CEILING | CWILLIAM | Approved | IVRS - Inspection :*/ INSPECTOR WILL CHECK SMOKE ALARM OPERATION ON FINAL. |
| 06/25/2004 | MECHANICAL - TEMP PWR FOR TEST | JMILITEL | Approved | IVRS - Inspection :*/ OK FOR TEMP POWER. |
| 06/25/2004 | PLUMBING - TEMP POWER FOR TEST | JSTANLEY | Approved | IVRS - Inspection :* |
| 06/25/2004 | BUILDING - TEMP POWER FOR TEST | RSUBA | Approved | IVRS - Inspection :* |
| 06/25/2004 | ELECTRIC - TEMP POWER FOR TEST | RSUBA | Approved | IVRS - Inspection :* |
| 06/28/2004 | TEP CLEARANCE - PM | JKOZUCH | Approved | |
| 07/01/2004 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :*/ OK FOR FINAL C OF O. |
| 07/01/2004 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | |
| 07/01/2004 | ELECTRIC - UNDERGROUND | RSUBA | Approved | |
| 07/01/2004 | PLUMBING - INTERMEDIATE | TRINIVJR | Approved | |
| 07/01/2004 | PLUMBING - ABOVE CEILING | TRINIVJR | Approved | |
| 07/01/2004 | FIRE - FINAL | LTHOMAS | Approved | 1) OK C OF O |
| 07/01/2004 | PLUMBING - ROOF DRAINS | TRINIVJR | Approved | IVRS - Inspection :* |
| 07/01/2004 | PLUMBING - YARD WTR LINE/TEST | TRINIVJR | Approved | IVRS - Inspection :* |
| 07/01/2004 | PLUMBING - FINAL | TRINIVJR | Approved | IVRS - Inspection :*/ 1) MUST CAULK FIXTURES. 2) MUST STRAP DISCHARGE DRAIN TO DISHWASHER. |
| 07/01/2004 | OUTDOOR LIGHTING FINAL | RSUBA | Approved | IVRS - Inspection :* |
| 07/01/2004 | ELECTRIC - FINAL | RSUBA | Approved | IVRS - Inspection :* |
| 07/01/2004 | ELECTRIC - CABLE DROP | RSUBA | Approved | IVRS - Inspection :* |
| 07/01/2004 | SIGN - FINAL | JSONKIN | Approved | IVRS - Inspection :* |
| 07/02/2004 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | |
| 07/02/2004 | ELECTRIC - TEMPORARY SERVICE | RHOLLAND | Approved | IVRS - Inspection :* |
| 07/02/2004 | U VALUE FOR WINDOW | RSUBA | Approved | IVRS - Inspection :* |
| 07/02/2004 | BUILDING - FINAL | RSUBA | Approved | IVRS - Inspection :* |
| 07/06/2004 | PERMIT FINALED | ACONNOR | Approved | |
| 07/06/2004 | NPPO - FINAL | ACONNOR | Approved | |
| 07/06/2004 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 07/06/2004 | ENGINEERING - FINAL | DROBERTS | Approved |