Permit: T04CM00297
Permit Details
Apply Date:
01/23/2004
Applicant:
ROBERT OTERO
Description:
ADDITION:MASTER BEDROOM & BATH
Permit Reviews
Permit Number - T04CM00297
Permit Status: Final
Permit Description: ADDITION:MASTER BEDROOM & BATH
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/23/2004 | PLANS OK TO SUBMIT - 3RD PARTY | 01/23/2004 | COMPLETED |
| 01/23/2004 | RESIDENTIAL BLDG/WWM | 02/13/2004 | COMPLETED |
| 07/01/2004 | RESUBMITTAL | 07/12/2004 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T04CM00297
Permit Status: Final
Permit Description: ADDITION:MASTER BEDROOM & BATH
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/23/2004 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T04CM00297
Permit Description: ADDITION:MASTER BEDROOM & BATH
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/12/2004 | ELECTRIC - CABLE DROP | DQUINN | Approved | IVRS - Inspection :* |
| 08/12/2004 | ELECTRIC - UFER | DQUINN | Approved | IVRS - Inspection :* |
| 08/13/2004 | TEP CLEARANCE - AM | JKOZUCH | Approved | |
| 08/19/2004 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | IVRS - Inspection :* |
| 08/20/2004 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | IVRS - Inspection :* |
| 10/07/2004 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | IVRS - Inspection :* |
| 10/07/2004 | BUILDING PRE-SLAB | DQUINN | Approved | IVRS - Inspection :* |
| 11/19/2004 | EXT METAL CLIPS/EXT SHEATHING | RCAMACHO | Approved | IVRS - Inspection : See detailed listing on site.| 999*/ 1) NAIL PROTECT PLUMBING 2) COMPLETE SHEAR |
| 11/19/2004 | ROOF NAILING | RCAMACHO | Approved | IVRS - Inspection :* |
| 01/26/2005 | U VALUE FOR WINDOW | DQUINN | Approved | IVRS - Inspection :* |
| 08/08/2005 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | IVRS - Inspection :* |
| 08/08/2005 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | IVRS - Inspection :* |
| 08/08/2005 | PLUMBING - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 08/09/2005 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 08/09/2005 | FRAMING | DQUINN | Approved | IVRS - Inspection :* |
| 08/23/2005 | STUCCO MESH | DQUINN | Approved | IVRS - Inspection :* |
| 03/10/2006 | PLUMBING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 03/10/2006 | ELECTRIC - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 03/10/2006 | BUILDING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 03/10/2006 | SHEET ROCK NAILING | DQUINN | Approved | IVRS - Inspection :* |
| 03/13/2006 | PERMIT FINALED | JWEATHER | Approved |