Permit: T03CM05865
Permit Details
Apply Date:
12/23/2003
Applicant:
SUMNER CONSTRUCTORS , R A
Description:
NEW:DUPLEX
Contractors:
- SUMNER CONSTRUCTORS , R A
Permit Reviews
Permit Number - T03CM05865
Permit Status: Final
Permit Description: NEW:DUPLEX
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/06/2004 | 3RD PARTY REVIEW-COMMERCIAL | 02/26/2004 | COMPLETED |
| 03/30/2004 | 3RD PARTY REVIEW-REVISION/OTHER | 05/06/2004 | COMPLETED |
| 12/23/2003 | PLANS OK TO SUBMIT - 3RD PARTY | 01/07/2004 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T03CM05865
Permit Status: Final
Permit Description: NEW:DUPLEX
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/23/2003 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T03CM05865
Permit Description: NEW:DUPLEX
Total Completed Inspections - 26
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/02/2004 | PLUMBING - ROUGH, SOIL | TRINIVJR | Approved | IVRS - Inspection 0000*/ 1) AIR PRESSURE TEST ON WASTE AND VENT SYSTEM IS OK 2) OK TO BACKFILL TRENCH 3) NOTE: BLDG DRAIN IS STUBBED OUT AT TWO WAY CLEANOUT ONLY |
| 03/03/2004 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection 0000* |
| 03/03/2004 | BUILDING PRE-SLAB | AMATHIES | Approved | |
| 03/03/2004 | EXCAVATION/LAYOUT REBAR & ZON | AMATHIES | Approved | |
| 05/12/2005 | ROOF NAILING | AMATHIES | Approved | IVRS - Inspection :* |
| 05/12/2005 | EXT METAL CLIPS/EXT SHEATHING | AMATHIES | Approved | IVRS - Inspection :* |
| 05/17/2005 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* APPROVED |
| 05/17/2005 | STUCCO MESH | AMATHIES | Approved | IVRS - Inspection :* |
| 05/17/2005 | U VALUE FOR WINDOW | AMATHIES | Approved | IVRS - Inspection :* |
| 05/17/2005 | FRAMING | AMATHIES | Approved | IVRS - Inspection :* |
| 05/20/2005 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | IVRS - Inspection :* |
| 06/01/2005 | PLUMBING - INTERMEDIATE | TRINIVJR | Approved | IVRS - Inspection :* 1) ALL CORRECTIONS HAVE BEEN MADE. |
| 06/01/2005 | SHEET ROCK NAILING | BSTEVENS | Approved | IVRS - Inspection :* |
| 06/15/2005 | PLUMBING - YARD WTR LINE/TEST | TRINIVJR | Approved | IVRS - Inspection :* 1) YARD WATER LINE FROM METERS TO BLDG SERVICE IS OK. 2) OK TO BACKFILL TRENCH. |
| 06/27/2005 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection :* |
| 06/27/2005 | ELECTRIC - CABLE DROP | RMAJUTA | Approved | IVRS - Inspection : See detailed listing on site.| 999* |
| 06/28/2005 | TEP CLEARANCE - AM | JKOZUCH | Approved | ECO # 1 ONLY |
| 07/06/2005 | TEP CLEARANCE - PM | JKOZUCH | Approved | ECO UNIT 2 |
| 08/10/2005 | PLUMBING - GAS PRESSURE TEST | TRINIVJR | Approved | |
| 08/10/2005 | PLUMBING - SEWER HCS CONNECT | TRINIVJR | Approved | |
| 08/10/2005 | PLUMBING - FINAL | TRINIVJR | Approved | IVRS - Inspection :* 1) PLUMBING FINAL IS OK 2) OK FOR C OF O |
| 08/10/2005 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection :* |
| 08/10/2005 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 08/10/2005 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 08/11/2005 | BUILDING - FINAL | AMATHIES | Approved | IVRS - Inspection :* |
| 08/17/2005 | PERMIT FINALED | JWEATHER | Approved |