Permit: T03CM05209
Permit Details
Apply Date:
11/03/2003
Applicant:
METRO PERMIT EXPRESS, INC
Description:
NEW:OFFICE
Architects:
- MASCIA, FRANK
Contractors:
- B F L CONSTRUCTION CO INC ,
Permit Reviews
Permit Number - T03CM05209
Permit Status: C of o
Permit Description: NEW:OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/04/2005 | REVISION | 01/04/2005 | COMPLETED |
01/12/2004 | 3RD PARTY REVIEW-RESIDENTIAL | 04/21/2004 | COMPLETED |
04/21/2004 | RESUBMITTAL | 06/25/2004 | COMPLETED |
07/30/2004 | REVISION | 08/04/2004 | COMPLETED |
08/12/2004 | 3RD PARTY REVIEW-REVISION/OTHER | 08/30/2004 | COMPLETED |
10/01/2004 | 3RD PARTY REVIEW-REVISION/OTHER | 01/04/2005 | COMPLETED |
11/03/2003 | PLANS OK TO SUBMIT - 3RD PARTY | 12/03/2003 | COMPLETED |
12/04/2003 | 3RD PARTY REVIEW-COMMERCIAL | 12/16/2003 | COMPLETED |
12/28/2004 | 3RD PARTY REVIEW-REVISION/OTHER-2ND | 01/04/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T03CM05209
Permit Status: C of o
Permit Description: NEW:OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
11/03/2003 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T03CM05209
Permit Description: NEW:OFFICE
Total Completed Inspections - 44
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/26/2004 | ELECTRIC - CONSTRUCTION POWER | JORTA | Approved | IVRS - Inspection :*/ 1) CALLED AND LEFT MESSAGE WITH KAREN |
07/28/2004 | TEP CLEARANCE - PM | JKOZUCH | Approved | |
08/03/2004 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :*/ 1) 3/0 UFER 20' COPPER |
08/09/2004 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | IVRS - Inspection :* LIGHT POLE BASES OK |
08/24/2004 | ELECTRIC - UNDERGROUND | JORTA | Approved | IVRS - Inspection :* SEE DETAILED LIST @ SIGHT. |
08/30/2004 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :*/ 1) PIPE WRAPS OK |
09/30/2004 | REINFORCED MASONRY PRE-GROUT | LHANLY | Approved | IVRS - Inspection :*APPROVED. |
10/08/2004 | ROOF NAILING | LHANLY | Approved | IVRS - Inspection :* |
10/14/2004 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
10/28/2004 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
10/28/2004 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
11/10/2004 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :*/VERIFICATION OF GRADE TURNED IN CORRECTION MADE |
11/10/2004 | PLUMBING - GAS PRESSURE TEST | RRICH | Approved | IVRS - Inspection :*/12 PSI AIR TEST FROM 2" STUB AT METER TO CAPS ON ROOF AT (9) ROOF TOP UNITS OK |
11/10/2004 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :*/WATER TEST WASTE & VENT THRU ROOF OK. 80 PSI AIR TEST ON H20 SYSTEM TO EXTERIOR SHUT OFFF VALVE OK. |
11/10/2004 | BUILDING PRE-SLAB | LHANLY | Approved | IVRS - Inspection :* |
11/10/2004 | FRAMING | LHANLY | Approved | IVRS - Inspection :* |
11/17/2004 | STUCCO MESH | LHANLY | Approved | IVRS - Inspection :* |
11/26/2004 | U VALUE FOR WINDOW | LHANLY | Approved | IVRS - Inspection :* |
11/26/2004 | ELECTRIC - INTERMEDIATE | RSUBA | Approved | IVRS - Inspection :* |
11/26/2004 | ELECTRIC - ABOVE CEILING | RSUBA | Approved | IVRS - Inspection :* |
11/29/2004 | SHEET ROCK NAILING | LHANLY | Approved | IVRS - Inspection :* |
01/05/2005 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
01/05/2005 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :*CHECKED SUPPLY, RETURN, EXHAUST, CONDENSATE DRAIN LINES, DUCT SMOKE DETECTORS. WILL TEST DETECTORS ON FINAL. OK FOR CEILING TILES |
01/06/2005 | TEP CLEARANCE - AM | RMAJUTA | Approved | OK CEC PER INSP SUBA 954-0161 |
01/13/2005 | BUILDING ABOVE CEILING | LHANLY | Approved | IVRS - Inspection :* |
01/19/2005 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
02/14/2005 | ELECTRIC - TEMP POWER FOR TEST | RMAJUTA | Approved | OK TEMP POWER PER SUBA |
02/17/2005 | OUTDOOR LIGHTING FINAL | RRICH | Approved | |
02/17/2005 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* ( 1) BACKFLOW CERTIFICATION TURNED IN. |
02/17/2005 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection :* |
02/17/2005 | PLUMBING - GAS PRESS TEST FNL | RRICH | Approved | IVRS - Inspection :* |
02/17/2005 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* |
02/18/2005 | ELECTRIC - CABLE DROP | RSUBA | Approved | |
02/18/2005 | ELECTRIC - FINAL | RSUBA | Approved | IVRS - Inspection :* |
02/23/2005 | FIRE - FINAL | LTHOMAS | Approved | |
02/23/2005 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
03/01/2005 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
03/03/2005 | CERTIFICATE OF OCCUPANCY | LHANLY | Approved | IVRS - Inspection :* APPROVED |
03/03/2005 | BUILDING - FINAL | LHANLY | Approved | IVRS - Inspection :* APPROVED |
03/28/2005 | ENGINEERING - FINAL | JSALINE | Approved | C OF O Approved. |
03/28/2005 | RIGHT OF WAY - FINAL | DLEE | Approved | |
03/31/2005 | PERMIT FINALED | DROBEY | Approved | |
03/31/2005 | LANDSCAPE - FINAL | ACONNOR | Approved | |
03/31/2005 | NPPO - FINAL | ACONNOR | Approved |