Permit: T03CM03955
Permit Details
Apply Date:
08/11/2003
Applicant:
LUGO JESUS FRANCISCO
Description:
ADDITION:REC ROOM
Permit Reviews
Permit Number - T03CM03955
Permit Status: Final
Permit Description: ADDITION:REC ROOM
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/11/2003 | RESIDENTIAL BLDG/ZONING/ENGINE | 08/11/2003 | COMPLETED |
| 11/09/2004 | REVISION | 11/09/2004 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T03CM03955
Permit Status: Final
Permit Description: ADDITION:REC ROOM
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/11/2003 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T03CM03955
Permit Description: ADDITION:REC ROOM
Total Completed Inspections - 16
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/10/2003 | EXCAVATION/LAYOUT REBAR & ZON | ROHAVER | Approved | IVRS - Inspection 0999*/ 1) REBAR DRIVEN INTO GROUND CANNOT BE TIED DIRECTLY TO STRUCTURAL HORIZONTAL REBAR 2) APPROVED 2-WAY CLEANOUT REQUIRED OUTSIDE OF WALL LINE 3) PVC PIPING NOT ALLOWED UNDER SLAB FOR WATER LINES 4) UNWRAP, UNCOVER ALL PIPING; COMPLETE TO PLAN, CODE, WATER TEST 5) NEED APPROVED FITTINGS CONNECTED INTO CLAY SEWER LINE 6) NO PLANS/PERMIT 7) STOPPED INSPECTION 8) CORRECT/COMPLETE AND RECALL 9) SUGGEST OBTAINING LICENSED PLUMBER TO COMPLETE PLUMBING |
| 11/26/2003 | PLUMBING - ROUGH, SOIL | ROHAVER | Approved | IVRS - Inspection 0999* |
| 11/26/2003 | STEM WALL/RETAINING WALL | ROHAVER | Approved | IVRS - Inspection 0000*/ 1) WRONG FITTINGS, WRONG SIZE PIPING, NO WATER TEST 2) NEED TO GET A LICENSED PLUMBER TO CORRECT ALL AND RECALL 3) STOPPED INSPECTION 4) WILL NEED TO HAVE PLUMBING COMPLETED AND APPROVED BEFORE FOOTING INSPECTION CAN BE MADE |
| 03/18/2004 | BUILDING PRE-SLAB | DBRITO | Approved | IVRS - Inspection 0000* |
| 08/17/2004 | REINFORCED MASONRY PRE-GROUT | FGREER | Approved | IVRS - Inspection :* |
| 11/15/2004 | FRAMING | FGREER | Approved | IVRS - Inspection :* |
| 11/15/2004 | ROOF NAILING | FGREER | Approved | IVRS - Inspection :* |
| 09/27/2005 | ELECTRIC - INTERMEDIATE | FVALENCI | Approved | IVRS - Inspection : See detailed listing on site.| 999* 1) PLAN CALLS FOR ELECTRICAL GFI AT SINK IN BATHROOM 2) PROVIDE WATER TEST AT TOP OUT DWV 3) PROVIDE DUCT/WORK FOR COOLER |
| 09/27/2005 | MECHANICAL - INTERMEDIATE | FVALENCI | Approved | IVRS - Inspection : See detailed listing on site.| 999* |
| 09/27/2005 | PLUMBING - INTERMEDIATE | FVALENCI | Approved | IVRS - Inspection : See detailed listing on site.| 999* |
| 06/15/2006 | MECHANICAL - FINAL | CTREVILL | Approved | IVRS - Inspection :* |
| 06/15/2006 | PLUMBING - FINAL | CTREVILL | Approved | IVRS - Inspection :* |
| 06/22/2006 | ELECTRIC - FINAL | EDURAZO | Approved | IVRS - Inspection :* |
| 06/22/2006 | BUILDING - FINAL | EDURAZO | Approved | IVRS - Inspection :* |
| 06/22/2006 | SHEET ROCK NAILING | EDURAZO | Approved | IVRS - Inspection :* |
| 06/23/2006 | PERMIT FINALED | JWEATHER | Approved |