Permit: T03CM01030
Permit Details
Apply Date:
02/27/2003
Applicant:
N/A
Description:
DUPLEX:TD# 15-70-31
Contractors:
- ORTIZ CONSTRUCTION L L C
Permit Reviews
Permit Number - T03CM01030
Permit Status: Final
Permit Description: DUPLEX:TD# 15-70-31
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/27/2003 | RESIDENTIAL BLDG/ZONING/FLOOD-WALK THRU | 02/27/2003 | COMPLETED |
| 04/16/2003 | REVISION | 04/16/2003 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T03CM01030
Permit Status: Final
Permit Description: DUPLEX:TD# 15-70-31
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/27/2003 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T03CM01030
Permit Description: DUPLEX:TD# 15-70-31
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/17/2003 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | ABS DWV UNDERGROUND INSTALLED PER REVISED APPROVED. PLAN OK WATER TEST ONE TO 10' OK TO COVER. |
| 04/17/2003 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection 0000* |
| 04/21/2003 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 04/21/2003 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 06/04/2003 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 06/04/2003 | EXT METAL CLIPS/EXT SHEATHING | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 06/23/2003 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection 0000* |
| 06/23/2003 | U VALUE FOR WINDOW | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 06/23/2003 | STUCCO MESH | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 06/24/2003 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | IVRS - Inspection 0000*/ 1) NOTE: NOW IS PERFECT TIME TO RUN CONDENSATE DOWN TO OUTSIDE PLANTER OR BATH ROOM SINK PIECE. CANNOT DUMP INTO SEWER VENT ON ROOF ANYMORE. HAVE MECH. CONST. ADDRESS IT NOW |
| 06/25/2003 | FRAMING | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 06/26/2003 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | IVRS - Inspection 0000* |
| 07/03/2003 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 09/12/2003 | ELECTRIC - FINAL | MCAPISTR | Approved | IVRS - Inspection 0000* |
| 09/12/2003 | ELECTRIC - TEMPORARY SERVICE | MCAPISTR | Approved | IVRS - Inspection 0000* |
| 09/12/2003 | ELECTRIC - CABLE DROP | MCAPISTR | Approved | IVRS - Inspection 0000* |
| 09/12/2003 | ELECTRIC - UFER | MCAPISTR | Approved | IVRS - Inspection 0000* |
| 09/15/2003 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection 0000* |
| 09/25/2003 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection 0000*/1) SOILS FOR BACKFILL ONLY. 2) CORRECTIONS MADE OK. 3) OK TO BACKFILL. |
| 10/28/2003 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection 0000* |
| 10/31/2003 | PLUMBING - FINAL | JSTANLEY | Approved | CORRECTIONS HAVE BEEN MADE AS PER LAST REQUEST. |
| 10/31/2003 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 11/03/2003 | PERMIT FINALED | AQUIROZ | Approved |