Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T02CM05903
Permit Details
Status:
Si_xpire
Type:
COMMERCIAL ALTERATION
Address:
2109 E HEDRICK DR
Address NEW:
2109 E HEDRICK DR
Apply Date:
12/24/2002
Applicant:
FORS ARCHITECTURE
Description:
Commercial addition
Contractors:
- HICKEY CONSTRUCTION
Permit Reviews
Permit Number - T02CM05903
Permit Status: Si_xpire
Permit Description: Commercial addition
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/20/2003 | RESUBMITTAL - SITE | 04/18/2003 | COMPLETED |
| 05/02/2003 | PLANS OK TO SUBMIT - 3RD PARTY | 05/02/2003 | COMPLETED |
| 05/05/2003 | 3RD PARTY REVIEW-COMMERCIAL TI | 05/21/2003 | COMPLETED |
| 05/22/2003 | 3RD PARTY REVIEW-COMMERCIAL TI | 06/30/2003 | COMPLETED |
| 06/30/2003 | RESUBMITTAL | 07/02/2003 | COMPLETED |
| 06/30/2003 | RESUBMITTAL - SITE | 07/02/2003 | COMPLETED |
| 11/03/2003 | 3RD PARTY REVIEW-REVISION/OTHER | 11/24/2003 | COMPLETED |
| 12/24/2002 | SITE | 03/20/2003 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T02CM05903
Permit Status: Si_xpire
Permit Description: Commercial addition
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 12/24/2002 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 07/01/2003 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
| 07/01/2003 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
| 07/01/2003 | SPECIAL INSPECTION IS REQUIRED FOR STRUCTURAL OBSERVATION. |
Completed Inspections
Permit Status: Si_xpire
Permit Number: T02CM05903
Permit Description: Commercial addition
Total Completed Inspections - 29
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/03/2003 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 07/16/2003 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection 0000*/ 1) ABS DWV UNDERGROUND FOR ADDITION OK, WATER TEST THRU ROOF OK 2) TIE-IN AT EXISTING OK 3) PLUMBER TO RED LINE AS BUILTS FOR TIE-IN TO EXISTING -2 PLACES 4) OK TO BACKFILL |
| 07/18/2003 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 08/27/2003 | ROOF NAILING | HLEYVA | Approved | IVRS - Inspection 0000* |
| 09/10/2003 | REINFORCED MASONRY PRE-GROUT | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 09/11/2003 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | IVRS - Inspection 0000*/ THERE IS NO WORK ABOVE CEILING GRID AND TILES. ALL WORK IS 4035 'ABOVE HARD LIDS.' DELETED 4036 AS PER CWILLIAM, 9/12/2003. |
| 09/11/2003 | ELECTRIC - ABOVE CEILING | MCAPISTR | Approved | IVRS - Inspection 0000* |
| 09/11/2003 | ELECTRIC - INTERMEDIATE | MCAPISTR | Approved | IVRS - Inspection 0000* |
| 09/16/2003 | FRAMING | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 09/19/2003 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 10/10/2003 | MECHANICAL - TEMP PWR FOR TEST | CWILLIAM | Approved | IVRS - Inspection 0000* |
| 10/13/2003 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | IVRS - Inspection 0000*/1) PRESSURE TEST OK. NEW PIPING OK. 2) TRANSITION OK. |
| 10/22/2003 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | |
| 10/22/2003 | FIRE - FINAL | JEGAN | Approved | IVRS - Inspection 0000*/ 1) OK C OF O |
| 10/22/2003 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection 0000* |
| 10/22/2003 | ELECTRIC - FINAL | MCAPISTR | Approved | IVRS - Inspection 0000* |
| 10/22/2003 | U VALUE FOR WINDOW | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 10/23/2003 | LANDSCAPE - FINAL | PGILBERT | Approved | |
| 11/14/2003 | SIGN - FINAL | DJOHNSTO | Approved | IVRS - Inspection 0000* |
| 11/14/2003 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection 0000*/ 1) ROOF DRAINS INSTALLED UNDER SLAB WITHOUT INSPECTION. INSPECTOR WITNESSED WATER TEST ON INTERMEDIATE. 2) PLBG FINAL OK. 3) OK FOR C OF O PENDING ANY OTHER INSPECTION. |
| 11/14/2003 | PLUMBING - GAS PRESS TEST FNL | RMYERS | Approved | IVRS - Inspection 0000* |
| 11/14/2003 | PLUMBING - ROOF DRAINS | RMYERS | Approved | IVRS - Inspection 0000* |
| 11/14/2003 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection 0000* |
| 11/14/2003 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection 0000* |
| 11/17/2003 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 11/24/2003 | ENGINEERING - FINAL | JBRUCKME | Approved | |
| 11/24/2003 | PLUMBING - TEMP POWER FOR TEST | RMYERS | Approved | |
| 11/24/2003 | ELECTRIC - TEMP POWER FOR TEST | MCAPISTR | Approved | |
| 11/24/2003 | BUILDING - TEMP POWER FOR TEST | AQUIROZ | Approved |