Permit: T02CM04190
Permit Details
Apply Date:
09/06/2002
Applicant:
N/A
Description:
NEW:RETAIL
Contractors:
- CHESTNUT CONSTRUCTION CORPORATIO
Permit Reviews
Permit Number - T02CM04190
Permit Status: C of o
Permit Description: NEW:RETAIL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/02/2003 | RESUBMITTAL | 05/29/2003 | COMPLETED |
| 05/29/2003 | SITE | 06/10/2003 | COMPLETED |
| 05/29/2003 | OTHER | 06/10/2003 | COMPLETED |
| 07/10/2003 | 3RD PARTY REVIEW-REVISION/OTHER | 07/24/2003 | COMPLETED |
| 09/06/2002 | 3RD PARTY REVIEW-COMMERCIAL | 04/22/2003 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T02CM04190
Permit Status: C of o
Permit Description: NEW:RETAIL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/06/2002 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T02CM04190
Permit Description: NEW:RETAIL
Total Completed Inspections - 42
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/02/2003 | ELECTRIC - UFER | HLEYVA | Approved | IVRS - Inspection 0000* |
| 07/03/2003 | STEM WALL/RETAINING WALL | HLEYVA | Approved | OK MAIN BLDG |
| 07/11/2003 | FIRE SPKLR - UG PIPING FLUSH | JEGAN | Approved | IVRS - Inspection 0999* |
| 07/11/2003 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | NEEDS UNDERGROUND PRESSURE TEST AND FLUSH |
| 07/11/2003 | FIRE SPKLR - UG, PIPING, HYDRO | JEGAN | Approved | IVRS - Inspection 0000* |
| 07/16/2003 | ELECTRIC - TEMPORARY POLE | RHOLLAND | Approved | IVRS - Inspection 0000* |
| 07/21/2003 | PLUMBING - ROUGH, SOIL | JSTANLEY | Approved | IVRS - Inspection 0000* PRE SLAB OK- LETTER ON CHANGE FOR WASTE LIVE ON RECORD |
| 07/21/2003 | BUILDING PRE-SLAB | RSUBA | Approved | IVRS - Inspection 0000*/ 1) BLDG OK TO POUR |
| 07/31/2003 | PLUMBING - SEWER HCS CONNECT | JSTANLEY | Approved | 1) SUBJECT TO LETTER ON EXISTING HCS 4" CLAY |
| 08/21/2003 | ELECTRIC - UNDERGROUND | RMAJUTA | Approved | IVRS - Inspection 0000*/ 1) 2-SIGNS, NORTH EAST CORNER 2-1" PVC'S AND GROUND ROD, SW CORNER 2-1" PVC'S AND GROUND ROD 2) 2 POLE BASES OK SOUTH SIDE |
| 08/29/2003 | PLUMBING - GAS PRESSURE TEST | JSTANLEY | Approved | IVRS - Inspection 0000*/ TEST OK. |
| 09/04/2003 | PLUMBING - INTERMEDIATE | JSTANLEY | Approved | IVRS - Inspection 0000*/ 1) TEST ON WASTE VENTS AND WATER OK |
| 09/05/2003 | FRAMING | LHANLY | Approved | IVRS - Inspection 0000* |
| 09/05/2003 | EXT METAL CLIPS/EXT SHEATHING | LHANLY | Approved | IVRS - Inspection 0000* |
| 09/10/2003 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection 0000*/ INSPECTED CONDENSATE DRAIN LINES. OK TO INSULATE. |
| 09/11/2003 | ELECTRIC - INTERMEDIATE | RMAJUTA | Approved | IVRS - Inspection 0000*/ 1) ENTRY COLUMNS (TWO) OK TO COVER LAST OF INTERMEDIATE |
| 09/12/2003 | PLUMBING - YARD WTR LINE/TEST | JSTANLEY | Approved | IVRS - Inspection 0000*/ 1) 2" WATER SERVICE ONLY 2) WILL NEED TO LOOK AT IRRIGATION LINE FROM METER TO BACKFLOW DEVICE 3) WILL REQUIRE TESTING ON BOTH DEVICES AT TIME OF FINAL |
| 09/12/2003 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 09/16/2003 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 09/17/2003 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection 0000* ON RETROFIT FOR EXSISTING 8' SCREEN WALL |
| 09/19/2003 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection 0000*/1) OK FOR TEMP POWER S.T.O.I. 2) ABOVE CEILING OK TO COVER. 3) HAVE PLUMBER REVIEW 511.2 94 UPC LOCATION AND ACCESS TO WATER HEATER. IF WATER HEATER IS ABOVE 8' AFF REQUIRES A PERMANENT LADDER OR STAIRWELL. |
| 09/19/2003 | STUCCO MESH | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 09/19/2003 | REINFORCED MASONRY PRE-GROUT | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 10/02/2003 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection 0000*/ 1) OK TO TILE |
| 10/08/2003 | MECHANICAL - ABOVE CEILING | CWILLIAM | Approved | IVRS - Inspection 0000* |
| 10/30/2003 | ENGINEERING - FINAL | JSALINE | Approved | |
| 10/30/2003 | FIRE - FINAL | JEGAN | Approved | IVRS - Inspection 0000* |
| 10/30/2003 | FIRE SPKLR - FINAL | JEGAN | Approved | IVRS - Inspection 0000*/ 1) OK C OF O |
| 10/30/2003 | PLUMBING - FINAL | JSTANLEY | Approved | IVRS - Inspection 0000* |
| 11/06/2003 | NPPO - FINAL | PGILBERT | Approved | |
| 11/06/2003 | LANDSCAPE - FINAL | PGILBERT | Approved | |
| 11/06/2003 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection 0000* |
| 11/06/2003 | OUTDOOR LIGHTING FINAL | RMAJUTA | Approved | IVRS - Inspection 0000*/ 1) VARIFICATION OF HEADS 2) SW LIGHT POLE COVER TO CLOSE TIGHT |
| 11/07/2003 | BUILDING - FINAL | AMATHIES | Approved | IVRS - Inspection 0000*/ OK TEMP C OF O. |
| 11/10/2003 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection 0000*/ 1) OK FINAL |
| 11/12/2003 | RIGHT OF WAY - FINAL | MOTERO | Approved | TEMP ONLY PENDING COMPLETION OF P I A |
| 11/12/2003 | SIGN - FINAL | JYBARRA | Approved | |
| 01/15/2004 | PERMIT FINALED | AMATHIES | Approved | |
| 01/15/2004 | FIRE SPKLR - OH PIPING & HYDRO | JEGAN | Approved | |
| 01/15/2004 | PLUMBING - GAS PRESS TEST FNL | JSTANLEY | Approved | |
| 01/15/2004 | PLUMBING - ROOF DRAINS | JSTANLEY | Approved | |
| 01/15/2004 | U VALUE FOR WINDOW | AMATHIES | Approved |