Permit: T02CM02654
Permit Details
Status:
C of o
Type:
COMMERCIAL ADDITION
Address:
5150 E 5TH ST BLDG #2
Address NEW:
5150 E 5TH ST BLDG #2
Apply Date:
05/30/2002
Applicant:
SOLOWAY DESIGNS
Description:
ADDITION:RITUAL ROOM
Architects:
- BAILEY, ROBERT GRIFFITH JR
Contractors:
- OLLANIK CONSTRUCTION
Permit Reviews
Permit Number - T02CM02654
Permit Status: C of o
Permit Description: ADDITION:RITUAL ROOM
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/22/2004 | REVISION | 01/23/2004 | COMPLETED |
| 03/03/2003 | REVISION | 03/03/2003 | COMPLETED |
| 05/30/2002 | COMMERCIAL NEW | 07/19/2002 | COMPLETED |
| 05/30/2002 | SITE | 07/19/2002 | COMPLETED |
| 07/14/2003 | REVISION | 07/15/2003 | COMPLETED |
| 09/24/2002 | RESUBMITTAL | 10/22/2002 | COMPLETED |
| 09/24/2002 | RESUBMITTAL - SITE | 11/06/2002 | COMPLETED |
| 10/28/2002 | RESUBMITTAL | 11/06/2002 | COMPLETED |
| 11/06/2002 | RESUBMITTAL | 11/13/2002 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T02CM02654
Permit Status: C of o
Permit Description: ADDITION:RITUAL ROOM
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/30/2002 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T02CM02654
Permit Description: ADDITION:RITUAL ROOM
Total Completed Inspections - 37
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/29/2003 | STEM WALL/RETAINING WALL | RSUBA | Approved | |
| 03/13/2003 | PLUMBING - ROUGH, SOIL | JSTANLEY | Approved | IVRS - Inspection 0000* |
| 04/01/2003 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | IVRS - Inspection 0000*OK #8 BONDS FOR HAND RAILS. |
| 06/11/2003 | ROOF NAILING | RSUBA | Approved | IVRS - Inspection 0000* |
| 08/06/2003 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection 0000*/ OK FOR SHEET ROCK. |
| 08/06/2003 | PLUMBING - ABOVE CEILING | JSTANLEY | Approved | IVRS - Inspection 0000*/TEST OK WASTE VENTS AND WATER. A BACKFLOW DEVICE WILL BE REQUIRED ON CROSS CONNECTION AT DORS(?) |
| 08/06/2003 | PLUMBING - INTERMEDIATE | JSTANLEY | Approved | IVRS - Inspection 0000* |
| 08/06/2003 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection 0000* |
| 08/06/2003 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection 0000* |
| 08/07/2003 | BUILDING ABOVE CEILING | RSUBA | Approved | IVRS - Inspection 0000* |
| 08/07/2003 | FRAMING | RSUBA | Approved | IVRS - Inspection 0000* |
| 08/07/2003 | EXT METAL CLIPS/EXT SHEATHING | RSUBA | Approved | IVRS - Inspection 0000* |
| 08/19/2003 | STUCCO MESH | RSUBA | Approved | IVRS - Inspection 0000* |
| 08/26/2003 | SHEET ROCK NAILING | RSUBA | Approved | IVRS - Inspection 0000* |
| 11/03/2003 | PLUMBING - SEWER HCS CONNECT | JSTANLEY | Approved | IVRS - Inspection 0000* |
| 11/19/2003 | PLUMBING - YARD WTR LINE/TEST | JSTANLEY | Approved | IVRS - Inspection 0000*/ PLEASE PROVIDE 12" OF COVER ON SITE WATER. NOTE: PLBR - SEE PLAN FOR BACKWATER VALVE ON SEWER. |
| 03/17/2004 | PLUMBING - FINAL | JSTANLEY | Approved | IVRS - Inspection 0000*/ FINAL OK STOI. FIELD TEST COMPLETE ON BACKFLOW DEVICE. |
| 03/23/2004 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection 0000*/ OK FOR FINAL C OF O. |
| 03/23/2004 | OUTDOOR LIGHTING FINAL | RHOLLAND | Approved | IVRS - Inspection 0000* |
| 03/23/2004 | ELECTRIC - UFER | RHOLLAND | Approved | IVRS - Inspection 0000* |
| 03/26/2004 | ENGINEERING - FINAL | JSALINE | Approved | C OF O APPROVED. |
| 03/26/2004 | U VALUE FOR WINDOW | RSUBA | Approved | IVRS - Inspection 0000* |
| 03/29/2004 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection 0000* |
| 04/02/2004 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection 0000* |
| 04/02/2004 | BUILDING - FINAL | HLEYVA | Approved | IVRS - Inspection 0000* |
| 04/02/2004 | BUILDING PRE-SLAB | HLEYVA | Approved | |
| 08/09/2004 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | |
| 08/09/2004 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 08/10/2004 | PERMIT FINALED | JMILITEL | Approved | |
| 08/10/2004 | MECHANICAL - PROGRESS | JMILITEL | Approved | |
| 08/10/2004 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | |
| 08/10/2004 | PLUMBING - GAS PRESS TEST FNL | JMILITEL | Approved | |
| 08/10/2004 | PLUMBING - GAS PRESSURE TEST | JMILITEL | Approved | |
| 08/10/2004 | PLUMBING - ROOF DRAINS | JMILITEL | Approved | |
| 08/10/2004 | ELECTRIC - CABLE DROP | RHOLLAND | Approved | |
| 08/10/2004 | REINFORCED MASONRY PRE-GROUT | HLEYVA | Approved | |
| 08/10/2004 | EXCAVATION/LAYOUT REBAR & ZON | HLEYVA | Approved |