Permit Details

Status:
C of o
Type:
COMMERCIAL ADDITION
Address:
4850 S PARK AV
Address NEW:
4850 S PARK AV
Apply Date:
05/06/2002
Applicant:
METRO PERMIT EXPRESS, INC
Description:
ADDITION:PACKAGING CENTER
Architects:
  • EGLIN, EVAN SAR
Contractors:
  • TRIUMPH BUILDERS SOUTHWEST LLC

Permit Reviews

Permit Number - T02CM02265
Permit Status: C of o
Permit Description: ADDITION:PACKAGING CENTER
Start Date Submittal Complete Date Status  
05/06/2002 SITE 06/27/2002 COMPLETED Review Details
05/06/2002 3RD PARTY REVIEW-COMMERCIAL 06/28/2002 COMPLETED Review Details
06/27/2002 RESUBMITTAL 07/23/2002 COMPLETED Review Details
06/28/2002 RESUBMITTAL 07/23/2002 COMPLETED Review Details
08/30/2002 REVISION 09/17/2002 COMPLETED Review Details
10/18/2002 REVISION 10/25/2002 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T02CM02265
Permit Status: C of o
Permit Description: ADDITION:PACKAGING CENTER
Total Outstanding Activity Conditions - 1
Date Name
05/06/2002 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T02CM02265
Permit Description: ADDITION:PACKAGING CENTER
Total Completed Inspections - 34
Date Description Inspector Results Comments
02/25/2002 MECHANICAL - UNDERGROUND CWILLIAM Approved
07/30/2002 PLUMBING - ROUGH, SOIL RMYERS Approved IVRS - Inspection 0000*1.) CORRECTION MADE OK. 2.) OK TO COVER.
08/08/2002 FIRE SPKLR - UG, PIPING, HYDRO LTHOMAS Approved NEED PLAN/PERMIT FOR FIRE SERVICE UNDERGROUND
08/12/2002 ELECTRIC - UFER JORTA Approved IVRS - Inspection 0000*
08/15/2002 PLUMBING - SEWER HCS CONNECT RMYERS Approved IVRS - Inspection 0000*1.) 4" SDR 35 FROM BLDG DRAIN TO TIE-IN OUT EXISTING OK 2.) WATER TEST FROM LOWEST TO HIGHEST POINT OK 3.) TRANSITION FITTINGS OK 4.) OK TO BACKFILL. 5.) WILL REQUIRE VERIFICATION OF GRADE BY ENGINEER BEFORE FINAL INSPECTION DON'T FORGET.
10/15/2002 BUILDING PRE-SLAB LHANLY Approved IVRS - Inspection 0000*
10/29/2002 ELECTRIC - UNDERGROUND MCAPISTR Approved IVRS - Inspection 0000*1.) U/G 4" PVC SECONDARY TRFMR. TO CT CAN.
11/04/2002 EXCAVATION/LAYOUT REBAR & ZON LHANLY Approved IVRS - Inspection 0000*
11/05/2002 PLUMBING - GAS PRESSURE TEST RMYERS Approved IVRS - Inspection 0000*
11/08/2002 PLUMBING - INTERMEDIATE RMYERS Approved IVRS - Inspection 0000*
12/05/2002 ELECTRIC - INTERMEDIATE JORTA Approved PAINT SHOP ABOVE CEILING OK EXCEPT BUS PACT WILL SEE LATER NEED NEUTRAL DISCONNECT LINKS
NEED NEUTRAL DISCONNECT LINKS. NEED MAIN BONDING JUMPER. NEED NEUTRAL BROUGHT DOWN TO EACH DISCONNECT. TRANSFORMER COMPROMISING WORKING
12/06/2002 BUILDING - TEMP POWER FOR TEST LHANLY Approved IVRS - Inspection 0000*
12/06/2002 SHEET ROCK NAILING LHANLY Approved IVRS - Inspection 0000*
12/06/2002 BUILDING ABOVE CEILING LHANLY Approved IVRS - Inspection 0000*
12/06/2002 FRAMING LHANLY Approved IVRS - Inspection 0000*I NEED WELD REPORTS ON CANOPIES.
12/06/2002 STEM WALL/RETAINING WALL LHANLY Approved IVRS - Inspection 0000*
12/08/2002 PLUMBING - TEMP POWER FOR TEST RMYERS Approved IVRS - Inspection 0000*
1.) APPROVAL FOR TEMP POWER WAS GIVEN ON 12/6/02
12/09/2002 MECHANICAL - TEMP PWR FOR TEST CWILLIAM Approved IVRS - Inspection 0000*
12/10/2002 RIGHT OF WAY - FINAL LLOPEZ Approved
12/10/2002 SIGN - FINAL DJOHNSTO Approved IVRS - Inspection 0000*
12/10/2002 ELECTRIC - TEMP POWER FOR TEST RMAJUTA Approved SUBJECT TO OTHER INSP & BOND.
12/11/2002 ENGINEERING - FINAL LMAKUS Approved
12/12/2002 ROOF NAILING LHANLY Approved IVRS - Inspection 0000*
12/13/2002 LANDSCAPE - FINAL PGILBERT Approved
12/13/2002 FIRE - FINAL LTHOMAS Approved
12/13/2002 FIRE SPKLR - FINAL LTHOMAS Approved
12/13/2002 FIRE SPKLR - OH PIPING & HYDRO LTHOMAS Approved
12/13/2002 FIRE SPKLR - UG PIPING FLUSH LTHOMAS Approved
12/20/2002 MECHANICAL - FINAL CWILLIAM Approved IVRS - Inspection 0000*
12/20/2002 MECHANICAL - INTERMEDIATE CWILLIAM Approved
12/23/2002 PLUMBING - FINAL RMYERS Approved IVRS - Inspection 0000*1.) PLUMBING FINAL OK
2.) OK FOR C OF O PENDING ANY OTHER INSPECTION.
12/23/2002 ELECTRIC - FINAL JORTA Approved IVRS - Inspection 0000*OK TEMP C OF O INSTALL ALL EQUIPMENT TO BE LISTED AND CALL FOR FINAL TO MATCH PLANS.
12/26/2002 BUILDING - FINAL LHANLY Approved IVRS - Inspection 0000*1.) THIS BUILDING IS COMPLETE EXCEPT FOR PLACEMENT OF EQUIPMENT IN SLOP. ELECTRICAL INSPECTOR MAY FINAL PERMIT WHEN EQUIPMENT HAS BEEN INSTALLED AND APPROVED.
03/14/2003 PERMIT FINALED LHANLY Approved

Documents

File Name Document Type  
None DOCUMENTS VIEW
None CONSTRPLANS VIEW