Permit Details

Status:
Final
Type:
COMMERCIAL NEW
Address NEW:
2245 E IRVINGTON RD
Apply Date:
11/14/2001
Applicant:
METRO PERMIT EXPRESS, INC
Description:
NEW:RETAIL
Architects:
  • MEEKS, LAWRENCE DALE
Contractors:
  • R A S BUILDERS

Permit Reviews

Permit Number - T01CM05608
Permit Status: Final
Permit Description: NEW:RETAIL
Start Date Submittal Complete Date Status  
01/09/2002 RESUBMITTAL 01/17/2002 COMPLETED Review Details
01/17/2002 RESUBMITTAL 01/22/2002 COMPLETED Review Details
05/16/2002 REVISION 05/29/2002 COMPLETED Review Details
11/14/2001 3RD PARTY REVIEW-COMMERCIAL 01/09/2002 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T01CM05608
Permit Status: Final
Permit Description: NEW:RETAIL
Total Outstanding Activity Conditions - 1
Date Name
11/14/2001 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T01CM05608
Permit Description: NEW:RETAIL
Total Completed Inspections - 41
Date Description Inspector Results Comments
01/25/2002 ELECTRIC - UFER JORTA Approved IVRS - Inspection 0000*
02/20/2002 PLUMBING - SEWER HCS CONNECT RMYERS Approved IVRS - Inspection 0000*
02/22/2002 PLUMBING - ROUGH, SOIL RMYERS Approved IVRS - Inspection 0000*1.) BLDG 3 ABS UNDERGROUND OK WATER TEST OK TIE IN TO MANHOLE OK 2.) OK TO BACKFILL.
02/28/2002 PLUMBING - YARD WTR LINE/TEST RMYERS Approved 1.) PVC YARDWATER FROM METER TO BLDG #3 OK 2.) CONNECTIONS OK 3.) OK TO COVER. 4.) WILL SEE RPBP CERTIFICATION ON FINAL.
03/07/2002 BUILDING ABOVE CEILING LHANLY Approved IVRS - Inspection 0000*
03/07/2002 ROOF NAILING LHANLY Approved IVRS - Inspection 0000*
03/07/2002 EXT METAL CLIPS/EXT SHEATHING LHANLY Approved IVRS - Inspection 0000*
04/23/2002 SHEET ROCK NAILING LHANLY Approved IVRS - Inspection 0000*
04/23/2002 FRAMING LHANLY Approved IVRS - Inspection 0000*
04/30/2002 MECHANICAL - INTERMEDIATE CWILLIAM Approved IVRS - Inspection 0000*
05/16/2002 PLUMBING - GAS PRESSURE TEST RMYERS Approved IVRS - Inspection 0000*
06/06/2002 MECHANICAL - TEMP PWR FOR TEST CWILLIAM Approved
06/07/2002 PLUMBING - TEMP POWER FOR TEST RMYERS Approved
06/07/2002 PLUMBING - ABOVE CEILING RMYERS Approved IVRS - Inspection 0000*1.) PLUMBING ABOVE CEILING OK OK TO COVER.
06/07/2002 ELECTRIC - TEMP POWER FOR TEST RMAJUTA Approved
06/07/2002 ELECTRIC - TEMPORARY SERVICE RMAJUTA Approved IVRS - Inspection 0000*SUBJECT TO BOND POSTED.
06/07/2002 ELECTRIC - ABOVE CEILING RMAJUTA Approved IVRS - Inspection 0000*
06/07/2002 BUILDING - TEMP POWER FOR TEST AMATHIES Approved
06/10/2002 MECHANICAL - ABOVE CEILING CWILLIAM Approved IVRS - Inspection 0000*
06/12/2002 PLUMBING - FINAL RMYERS Approved IVRS - Inspection 0000*1.) CORRECTION MADE OK 2.) PLUMBING FINAL OK 3.) OK FOR C OF O PENDING ANY OTHER INSPECTION.
06/12/2002 PLUMBING - INTERMEDIATE RMYERS Approved
06/13/2002 MECHANICAL - FINAL CWILLIAM Approved IVRS - Inspection 0000*
06/17/2002 FIRE - FINAL LTHOMAS Approved
06/17/2002 FIRE SPKLR - FINAL LTHOMAS Approved
06/17/2002 FIRE SPKLR - OH PIPING & HYDRO LTHOMAS Approved
06/17/2002 FIRE SPKLR - UG PIPING FLUSH LTHOMAS Approved
06/17/2002 FIRE SPKLR - UG, PIPING, HYDRO LTHOMAS Approved
06/18/2002 RIGHT OF WAY - FINAL LLOPEZ Approved
06/18/2002 REINFORCED MASONRY PRE-GROUT LHANLY Approved IVRS - Inspection 0000*
06/18/2002 BUILDING PRE-SLAB LHANLY Approved IVRS - Inspection 0000*
06/18/2002 STEM WALL/RETAINING WALL LHANLY Approved IVRS - Inspection 0000*
06/18/2002 EXCAVATION/LAYOUT REBAR & ZON LHANLY Approved IVRS - Inspection 0000*
07/01/2002 SIGN - FINAL JYBARRA Approved
07/23/2002 ELECTRIC - FINAL MCAPISTR Approved IVRS - Inspection 0000*
07/23/2002 ELECTRIC - INTERMEDIATE MCAPISTR Approved
07/23/2002 ELECTRIC - UNDERGROUND MCAPISTR Approved
07/25/2002 ENGINEERING - FINAL DROBERTS Approved
07/26/2002 NPPO - FINAL JLINVILL Approved
07/26/2002 LANDSCAPE - FINAL JLINVILL Approved
08/05/2002 PERMIT FINALED LHANLY Approved
08/05/2002 BUILDING - FINAL LHANLY Approved SPECAIL INSPECTION REPORTS REVIEWED AND ACCEPTED OK FOR C OF O.