Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Closed
Type:
COMMERCIAL OTHER
Address:
260 S CHURCH AV
Apply Date:
08/20/2001
Applicant:
M 3 ENGINEERING AND CONSTRUCTION
Description:
REPLACE:SWITCH GEAR
Contractors:
  • M 3 ENGINEERING AND CONSTRUCTION

Permit Reviews

Permit Number - T01CM04087
Permit Status: Closed
Permit Description: REPLACE:SWITCH GEAR
Start Date Submittal Complete Date Status  
02/07/2003 REVISION 02/11/2003 COMPLETED Review Details
04/24/2003 REVISION 05/20/2003 COMPLETED Review Details
08/20/2001 OTHER 10/01/2001 COMPLETED Review Details
10/08/2001 RESUBMITTAL 10/18/2001 COMPLETED Review Details
12/23/2002 REVISION 02/07/2003 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T01CM04087
Permit Status: Closed
Permit Description: REPLACE:SWITCH GEAR
Total Outstanding Activity Conditions - 1
Date Name
08/20/2001 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Closed
Permit Number: T01CM04087
Permit Description: REPLACE:SWITCH GEAR
Total Completed Inspections - 9
Date Description Inspector Results Comments
02/03/2003 ELECTRIC - PROGRESS RMAJUTA Approved IVRS - Inspection 0000*1.) MEETING WITH GILBER ELECT, CITY OF TUCSON FACITITES MANAGEMENT, TEP, M3 ENGINEERING TO REVIEW INSTALLATION OF TEP TRANSFORMERS AND NEW SWITCH GREAR REPLACEMENT.
03/07/2003 ELECTRIC - UNDERGROUND DSANTACR Approved IVRS - Inspection 0000*OK SECONDARY UNDER SLAB AND CAD WELD TO COUNTER POISE GROUND SYSTEM.
08/12/2003 EXCAVATION/LAYOUT REBAR & ZON AMATHIES Approved IVRS - Inspection 0000*
09/05/2003 PLUMBING - GAS PRESS TEST FNL TRINIVJR Approved IVRS - Inspection 0000*/ 1) GAS PRESSURE TEST IS OK 2) GAS SHUT OFF VALVES OK 3) NOTE: REGULATOR LOCATION IS CONSIDERED OPEN AIR SPACE
09/09/2003 ELECTRIC - FINAL DSANTACR Approved IVRS - Inspection 0000*
12/21/2007 BUILDING - FINAL LHANLY Approved equipment mounting and slab ok.
12/21/2007 ELECTRIC - SERVICE UPGRADE LHANLY Approved reference final approval 09/03
12/21/2007 ELECTRIC - INTERMEDIATE LHANLY Approved reference final approval 09/03
12/21/2007 PLUMBING - FINAL LHANLY Approved the only plumbing was for the gas piping which was approved in 09/03