Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T01CM03996
Permit Details
Apply Date:
08/15/2001
Applicant:
EGLIN, EVAN SAR
Description:
OFFICE:NEW
Architects:
- EGLIN, EVAN SAR
Contractors:
- SHULL JONES BUILDERS ,
Permit Reviews
Permit Number - T01CM03996
Permit Status: Final
Permit Description: OFFICE:NEW
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/24/2003 | REVISION | 01/31/2003 | COMPLETED |
01/29/2002 | SITE | 02/22/2002 | COMPLETED |
02/26/2002 | RESUBMITTAL | 02/27/2002 | COMPLETED |
02/27/2002 | RESUBMITTAL | 02/27/2002 | COMPLETED |
08/15/2001 | 3RD PARTY REVIEW-COMMERCIAL | 02/27/2002 | COMPLETED |
11/01/2001 | SITE | 12/18/2001 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T01CM03996
Permit Status: Final
Permit Description: OFFICE:NEW
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/15/2001 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T01CM03996
Permit Description: OFFICE:NEW
Total Completed Inspections - 35
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/17/2002 | STEM WALL/RETAINING WALL | AMATHIES | Approved | IVRS - Inspection 0000* |
06/21/2002 | PLUMBING - ROUGH, SOIL | TRINIVJR | Approved | 1.) SOIL WATER TEST IS OK 2.) HCS CONNECTION TO SEWER @ P.L. IS OK 3.) OK TO BACKFILL TRENCH. |
06/27/2002 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection 0000* |
06/28/2002 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection 0000*NOTES 2 GROUND RODS INSTALLED NOT PER PLAN, BUT MEETS N.E.C. ALSO APPROVED BY SMYTH, P.E. |
07/10/2002 | BUILDING PRE-SLAB | LHANLY | Approved | IVRS - Inspection 0000* 1.) SOIL DENSITY REPORT NOT YET AVAILABLE FIELD TEST INDICATES 100%, 95% NECESSARY. 2.) CONTROL JOINTS TO BE SAW CUT PER CONTRACTORS OPTION. 3.) PLUMBING WRAP IN PLACE. |
10/09/2002 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection 0999* |
10/09/2002 | EXT METAL CLIPS/EXT SHEATHING | AQUIROZ | Approved | IVRS - Inspection 0000* |
10/30/2002 | PLUMBING - INTERMEDIATE | TRINIVJR | Approved | 1.) SOIL WATER TEST IS OK 2.) OVERHEAD WATER DISTRIBUTION IS OK 3.) RAIN LEADER WATER TEST IS OK 4.) OK FOR DRYWALL UPON BLDG. INSPECTORS APPROVAL. 5.) NOTE: MUST SEE INSTALLATION OF CLOSET RINGS PRIOR TO SETTING CLOSETS. |
10/30/2002 | FRAMING | AQUIROZ | Approved | IVRS - Inspection 0000* |
11/12/2002 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection 0000* |
11/13/2002 | EXCAVATION/LAYOUT REBAR & ZON | HLEYVA | Approved | IVRS - Inspection 0000*OK @ RETAINING WALL @ FRONT & DUMPSTER WALL FTG. |
11/18/2002 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection 0000*INSPECTED RESTROOMS & SHAFTS OK TO COVER. |
11/18/2002 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection 0000* |
11/25/2002 | REINFORCED MASONRY PRE-GROUT | AQUIROZ | Approved | IVRS - Inspection 0000*1ST LIFT. |
12/05/2002 | STUCCO MESH | HLEYVA | Approved | IVRS - Inspection 0000* |
01/27/2003 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection 0000* |
01/28/2003 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | |
01/28/2003 | PLUMBING - FINAL | TRINIVJR | Approved | 1.) PLBG FINAL IS OK 2.) OK FOR C OF O. |
01/28/2003 | PLUMBING - SEWER HCS CONNECT | TRINIVJR | Approved | |
01/28/2003 | PLUMBING - YARD WTR LINE/TEST | TRINIVJR | Approved | 1.) PLBG. FINAL IS OK 2.) OK FOR C OF O. |
01/28/2003 | PLUMBING - ABOVE CEILING | TRINIVJR | Approved | |
01/29/2003 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection 0000* |
01/29/2003 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection 0000* |
02/19/2003 | ENGINEERING - FINAL | JBRUCKME | Approved | |
02/25/2003 | LANDSCAPE - FINAL | PGILBERT | Approved | |
02/25/2003 | FIRE - FINAL | LTHOMAS | Approved | |
02/25/2003 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
02/25/2003 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
02/25/2003 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
02/25/2003 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
02/27/2003 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection 0000*OK FINAL. |
02/27/2003 | ELECTRIC - TEMPORARY SERVICE | RHOLLAND | Approved | |
02/27/2003 | ELECTRIC - CABLE DROP | RHOLLAND | Approved | |
02/27/2003 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection 0000* |
02/27/2003 | BUILDING - FINAL | HLEYVA | Approved | IVRS - Inspection 0000*OK FOR C OF O. |