Permit: T01CM03629
Permit Details
Apply Date:
07/24/2001
Applicant:
N/A
Description:
NEW APT BUILDING #5
Contractors:
- HAYES CONSTRUCTION INC , THOMAS
Permit Reviews
Permit Number - T01CM03629
Permit Status: C of o
Permit Description: NEW APT BUILDING #5
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/26/2002 | REVISION | 03/29/2002 | COMPLETED |
| 07/24/2001 | COMMERCIAL NEW | 09/14/2001 | COMPLETED |
| 09/14/2001 | RESUBMITTAL | 10/19/2001 | COMPLETED |
| 10/19/2001 | RESUBMITTAL | 10/31/2001 | COMPLETED |
| 10/31/2001 | RESUBMITTAL | 10/31/2001 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T01CM03629
Permit Status: C of o
Permit Description: NEW APT BUILDING #5
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/24/2001 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T01CM03629
Permit Description: NEW APT BUILDING #5
Total Completed Inspections - 32
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/01/2001 | ELECTRIC - UFER | MCAPISTR | Approved | IVRS - Inspection 0000* |
| 11/01/2001 | EXCAVATION/LAYOUT REBAR & ZON | AMATHIES | Approved | IVRS - Inspection 0000* |
| 11/09/2001 | STEM WALL/RETAINING WALL | EMONAHAN | Approved | IVRS - Inspection 0000* |
| 12/12/2001 | PLUMBING - ROUGH, SOIL | JSTANLEY | Approved | IVRS - Inspection 0000*TEST OK ON ABS CALL FOR PRE SLAB WATER & WRAP. |
| 12/19/2001 | PLUMBING - SEWER HCS CONNECT | JSTANLEY | Approved | IVRS - Inspection 0000* |
| 01/03/2002 | BUILDING PRE-SLAB | EMONAHAN | Approved | IVRS - Inspection 0000* |
| 01/29/2002 | PLUMBING - YARD WTR LINE/TEST | JSTANLEY | Approved | IVRS - Inspection 0000$ |
| 02/22/2002 | EXT METAL CLIPS/EXT SHEATHING | AMATHIES | Approved | IVRS - Inspection 0000* |
| 03/07/2002 | ROOF NAILING | AMATHIES | Approved | IVRS - Inspection 0000* |
| 03/27/2002 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | IVRS - Inspection 0000*BLDG 5 AS PER DISCUSSION REGISTER BOXES, 2ND TOP FLR. NEED TO BE INSULATED. |
| 03/27/2002 | PLUMBING - GAS PRESSURE TEST | FMCCLURE | Approved | IVRS - Inspection 0000*3 UNITS |
| 03/27/2002 | PLUMBING - INTERMEDIATE | FMCCLURE | Approved | IVRS - Inspection 0000*3 UNITS. |
| 03/27/2002 | FRAMING | AMATHIES | Approved | IVRS - Inspection 0000* |
| 04/11/2002 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection 0000*OK WALLS |
| 04/22/2002 | SHEET ROCK NAILING | AMATHIES | Approved | IVRS - Inspection 0000* |
| 04/22/2002 | STUCCO MESH | AMATHIES | Approved | IVRS - Inspection 0000* |
| 07/23/2002 | MECHANICAL - TEMP PWR FOR TEST | CWILLIAM | Approved | TEMP POWER TEST. |
| 07/25/2002 | NPPO - FINAL | JLINVILL | Approved | |
| 07/25/2002 | SIGN - FINAL | JYBARRA | Approved | |
| 07/25/2002 | LANDSCAPE - FINAL | JLINVILL | Approved | |
| 07/26/2002 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | |
| 07/26/2002 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 07/26/2002 | MECHANICAL - FINAL | CWILLIAM | Approved | |
| 07/26/2002 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection 0000* |
| 07/30/2002 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection 0000*1.) CORRECTION MADE OK 2.) PLUMBING FINAL OK 3.) OK FOR C OF O PENDING ANY OTHER INSPECTIONS 4.) FINAL INSPECTOR TO LEAVE UCC. |
| 07/30/2002 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection 0000*OK FINAL. |
| 07/30/2002 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | IVRS - Inspection 0000* |
| 07/30/2002 | BUILDING - FINAL | AMATHIES | Approved | IVRS - Inspection 0000* |
| 08/01/2002 | PERMIT FINALED | AMATHIES | Approved | |
| 08/01/2002 | FIRE - FINAL | LTHOMAS | Approved | |
| 08/01/2002 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 08/01/2002 | U VALUE FOR WINDOW | AMATHIES | Approved |