Permit: T01CM01139
Permit Details
Apply Date:
03/08/2001
Applicant:
H FIVE CONSTRUCTION
Description:
ADDITION:LIVING ROOM/CLOSET/STORAGE
Contractors:
- H FIVE CONSTRUCTION
Permit Reviews
Permit Number - T01CM01139
Permit Status: Final
Permit Description: ADDITION:LIVING ROOM/CLOSET/STORAGE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/08/2001 | RESIDENTIAL BLDG/ZONING/FLOOD | 03/08/2001 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T01CM01139
Permit Description: ADDITION:LIVING ROOM/CLOSET/STORAGE
Total Completed Inspections - 11
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/30/2001 | BUILDING PRE-SLAB | RFREIDIN | Approved | IVRS - Inspection 0000* |
| 03/30/2001 | EXCAVATION/LAYOUT REBAR & ZON | RFREIDIN | Approved | IVRS - Inspection 0000*/GAS LINE TO BE REMOVED AT LATER DATE. |
| 04/13/2001 | ROOF NAILING | RFREIDIN | Approved | IVRS - Inspection 0000* |
| 04/13/2001 | EXT METAL CLIPS/EXT SHEATHING | RFREIDIN | Approved | IVRS - Inspection 0000*/OK 3 2 X 6 AT SLIDING DOOR HEADER CAN BE A FLUSH BEAN |
| 05/11/2001 | SHEET ROCK NAILING | RFREIDIN | Approved | IVRS - Inspection 0000* |
| 05/11/2001 | FRAMING | RFREIDIN | Approved | IVRS - Inspection 0000* |
| 09/14/2001 | PERMIT FINALED | RFREIDIN | Approved | |
| 09/14/2001 | PLUMBING - FINAL | RFREIDIN | Approved | IVRS - Inspection 0000* |
| 09/14/2001 | PLUMBING - GAS PRESSURE TEST | RFREIDIN | Approved | IVRS - Inspection 0000* |
| 09/14/2001 | ELECTRIC - FINAL | RFREIDIN | Approved | IVRS - Inspection 0000* |
| 09/14/2001 | BUILDING - FINAL | RFREIDIN | Approved | IVRS - Inspection 0000* |