Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T00CM06088
Permit Details
Apply Date:
12/19/2000
Applicant:
N/A
Description:
NEW:APARTMENTS BLDG 4
Architects:
- ACORN, KIM BRIAN
Contractors:
- T A-WALLICK LLC
Permit Reviews
Permit Number - T00CM06088
Permit Status: C of o
Permit Description: NEW:APARTMENTS BLDG 4
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/02/2001 | REVISION | 11/26/2001 | COMPLETED |
12/19/2000 | 3RD PARTY REVIEW-COMMERCIAL | 11/21/2001 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T00CM06088
Permit Status: C of o
Permit Description: NEW:APARTMENTS BLDG 4
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/19/2000 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T00CM06088
Permit Description: NEW:APARTMENTS BLDG 4
Total Completed Inspections - 34
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/14/2002 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection 0000*1.) ABS UNDERGROUND OK WATER TEST RISERS ONLY ONE TO TEN FEET. 2.) OK TO BACKFILL. |
02/15/2002 | ELECTRIC - UFER | JORTA | Approved | IVRS - Inspection 0000*2 SEPARATE UFER WILL REQUIRE RODS AND OTHER AVAILABLE ELECTRODER UFER -NOT STANDING ALONE ON THIS PROJECT. |
02/15/2002 | BUILDING PRE-SLAB | LHANLY | Approved | IVRS - Inspection 0000* |
02/15/2002 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | IVRS - Inspection 0000* |
04/10/2002 | ROOF NAILING | LHANLY | Approved | IVRS - Inspection 0000* |
04/10/2002 | EXT METAL CLIPS/EXT SHEATHING | LHANLY | Approved | IVRS - Inspection 0000* |
04/25/2002 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection 0000*1.) YARD WATE CONNECTIONS AT METER OK OK TO COVER 2.) WILL CHECK CERTIFICATION OF RPBP ON FINAL. |
05/08/2002 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | IVRS - Inspection 0000*BLDG #4. |
05/15/2002 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection 0000*1.) ABS DWV FIRST AND SECOND FLOOR OK WATER TEST OK 2.) CPVC FIRST AND SECOND FLOOR OK PRESSURE TEST OK 3.) TUBS OK CLOSET FLANGES OK 4.) ROOF DRAINS OK WATER TEST OK 5.) OK TO COVER ALL AREAS. |
05/15/2002 | ELECTRIC - INTERMEDIATE | RMAJUTA | Approved | IVRS - Inspection 0000* |
05/21/2002 | STUCCO MESH | LHANLY | Approved | IVRS - Inspection 0000* |
05/21/2002 | FRAMING | LHANLY | Approved | IVRS - Inspection 0000* INSULATION MUST BE INSTALLED BEHIND TUBS. |
05/30/2002 | SHEET ROCK NAILING | LHANLY | Approved | IVRS - Inspection 0000* |
06/19/2002 | ELECTRIC - CABLE DROP | JORTA | Approved | IVRS - Inspection 0000*WILL NEED TO HAVE COMMON GROUNDING ELECTRODE SYSTEM BETWEEN SERVICE. |
07/30/2002 | ELECTRIC - TEMP POWER FOR TEST | RMAJUTA | Approved | IVRS - Inspection 0000* |
08/05/2002 | MECHANICAL - FINAL | CWILLIAM | Approved | |
08/05/2002 | MECHANICAL - TEMP PWR FOR TEST | CWILLIAM | Approved | |
08/06/2002 | ELECTRIC - FINAL | JORTA | Approved | IVRS - Inspection 0000* |
08/07/2002 | PLUMBING - TEMP POWER FOR TEST | RMYERS | Approved | IVRS - Inspection 0000*OK FOR TEMP POWER. |
08/14/2002 | FIRE - FINAL | LTHOMAS | Approved | |
08/14/2002 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
08/14/2002 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
08/14/2002 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
08/15/2002 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
08/15/2002 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection 0000* |
08/15/2002 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection 0000*1.) BLDG TIE-IN INSPECTED AT TIME OF SITE SEWER 2.) PLUMBING FINAL OK 3.) OK FOR C OF O PENDING ANY OTHER INSPECTIONS. |
08/15/2002 | BUILDING - FINAL | LHANLY | Approved | IVRS - Inspection 0000*1.) MECHANICAL & ELECTRIC APPROVED. 2.) PLUMBING NOT YET FINALED. 3.) FIRE WANTS ENUNCIATORS. 4.) REMOVE DEAD TEMP POWER PANEL BY 4103. |
08/15/2002 | U VALUE FOR WINDOW | LHANLY | Approved | IVRS - Inspection 0000* |
08/16/2002 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | |
08/16/2002 | SIGN - FINAL | JYBARRA | Approved | |
08/26/2002 | ENGINEERING - FINAL | DROBERTS | Approved | TEMPORARY C OF O APPROVED, FINAL NOT TO BE GIVEN UNTIL THE FINAL GRADING INSPECTION #9190 FOR T01BU01801 HAS BEEN COMPLETED AND APPROVED |
01/29/2003 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | |
01/30/2003 | PERMIT FINALED | LHANLY | Approved | |
01/30/2003 | BUILDING - TEMP POWER FOR TEST | LHANLY | Approved |