Permit: T00CM00711
Permit Details
Apply Date:
02/14/2000
Applicant:
KURATH, JOHN ROBERT
Description:
ADA COMFORT STATION
Architects:
- KURATH, JOHN ROBERT
Contractors:
- TUCSON BUILDING AND REMODELING I
Permit Reviews
Permit Number - T00CM00711
Permit Status: Final
Permit Description: ADA COMFORT STATION
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/24/2001 | RESUBMITTAL | 02/07/2001 | COMPLETED |
| 02/13/2001 | RESUBMITTAL | 08/07/2001 | COMPLETED |
| 07/31/2000 | COMMERCIAL TI | 01/24/2001 | COMPLETED |
| 08/08/2001 | REVISION | 10/31/2001 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T00CM00711
Permit Description: ADA COMFORT STATION
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/21/2001 | ELECTRIC - UFER | RMAJUTA | Approved | IVRS - Inspection 0000$#2 COPPER APPROVED. |
| 10/04/2001 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | IVRS - Inspection 0000* |
| 10/08/2001 | ELECTRIC - UNDERGROUND | RMAJUTA | Approved | IVRS - Inspection 0000*PARTIAL APPROVED. 1-2 PVC FEEDER FROM BOOSTER ST TO BLDG. 1 2 1/2" PVC FROM OUTSIDE DISCONNECT TO PNL A. |
| 10/12/2001 | STEM WALL/RETAINING WALL | LHANLY | Approved | IVRS - Inspection 0000* |
| 10/15/2001 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection 0000*1.) 4" SCH 40 PVC WATER FROM BOOSTER PUMP TO WITHIN 10" OF RPBP ENCLOSURE OK PRESSURE TEST OK 2.) OK TO COVER. |
| 10/19/2001 | ELECTRIC - INTERMEDIATE | JORTA | Approved | IVRS - Inspection 0000*PARTIAL IN WALLS 1ST LIFT. |
| 10/22/2001 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection 0000*1.) PRE-POUR INSPECTION OK FLOOR DRAINS OK TRAP PRIMERS OK PIPE WRAP OK 2.) OK TO COVER. |
| 10/22/2001 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection 0000* |
| 10/25/2001 | BUILDING PRE-SLAB | LHANLY | Approved | IVRS - Inspection 0000* |
| 11/15/2001 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection 0000*1.) SDR35 BLDG SEWER OK WATER TEST OK TRANSITION FITTINGS OK TIE IN TO MAIN OK TIE IN TO BLDG DRAIN OK 2.) OK TO BACKFILL. |
| 12/04/2001 | REINFORCED MASONRY PRE-GROUT | LHANLY | Approved | IVRS - Inspection 0000* |
| 12/19/2001 | ELECTRIC - CABLE DROP | JORTA | Approved | IVRS - Inspection 0000*PRIMARY CONDUIT -4" APPROVED COMPLETE. |
| 01/15/2002 | FRAMING | LHANLY | Approved | IVRS - Inspection 0000* |
| 02/11/2002 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection 0000*1.) PLUMBING FINAL OK 2.) OK FOR C OF O PENDING ANY OTHER INSPECTION AND VERIFICATION OF CERTIFICATION OF RPPBP. |
| 02/11/2002 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection 0000* |
| 02/11/2002 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection 0000* |
| 02/11/2002 | ELECTRIC - FINAL | JORTA | Approved | IVRS - Inspection 0000* |
| 02/11/2002 | ELECTRIC - ABOVE CEILING | JORTA | Approved | |
| 02/12/2002 | BUILDING - FINAL | LHANLY | Approved | IVRS - Inspection 0000* |
| 02/12/2002 | ROOF NAILING | LHANLY | Approved | IVRS - Inspection 0000* |
| 02/14/2002 | PERMIT FINALED | TGRIFFUS | Approved |