Description:
*Revision #1 (shade canopy/grade) started 8/17/24.* Site/Grading - New community building and three new residence buildings.
Permit Reviews
Permit Number - DP22-0145
Permit Status: Issued
Permit Description: *Revision #1 (shade canopy/grade) started 8/17/24.* Site/Grading - New community building and three new residence buildings.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/30/2022 | DEV PKG - OK TO SUBMIT | 06/15/2022 | COMPLETED |
06/15/2022 | DEV PKG | 08/26/2022 | COMPLETED |
08/17/2024 | DEVELOPMENT PACKAGE REVIEW v.1 | 09/11/2024 | APPROVED |
11/07/2022 | DEVELOPMENT PACKAGE REVIEW v.1 | 12/28/2022 | REQUIRES RESUBMIT |
01/09/2023 | DEVELOPMENT PACKAGE REVIEW v.2 | 02/28/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - DP22-0145
Permit Status: Issued
Permit Description: *Revision #1 (shade canopy/grade) started 8/17/24.* Site/Grading - New community building and three new residence buildings.
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/08/2023 | Approval from ES is required for APCs, please reach out to andy.vera@tucsonaz.gov |
Outstanding Inspections
Permit Status: Issued
Permit Number: DP22-0145
Permite Description: *Revision #1 (shade canopy/grade) started 8/17/24.* Site/Grading - New community building and three new residence buildings.
Total Outstanding Inspections - 9
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/19/2024 | PDSD Site/Engineering Division - Landscaping | N/A | Not Ready | contractor working 0n vertical aspects |
03/19/2024 | SITE - Zoning Final | N/A | Canceled | no zoning issues noted |
07/02/2024 | SITE - Sign Footer/Setback/Excavation Layout/Rebar | N/A | Not Ready | Contractor will reschedule |
09/20/2024 | ENGR - Drainage Structures | N/A | Not Ready | No one on the site at this time it is 3:25 PM Friday afternoon. Reschedule this inspection for next week if it is still required. |
09/20/2024 | PDSD Site/Engineering Division - NPPO | N/A | Not Ready | No one on the site at this time it is 3:25 PM Friday afternoon. Reschedule this inspection for next week if it is still required. |
10/11/2024 | For trash and recycling enclosures | N/A | Partial Pass | Looked at the Approach Slab and the curb and sidewalk for the Trash Enclosure approach access, all ready to be poured. I also pointed out a couple of areas when the sidewalk change of directions are non-compliant just south of the trash enclosure. The contractor Tofel Dent will remove and replace these sections. |
09/30/2024 | N/A | Not Ready | Contractor needs to grade for water harvesting area all around the building | |
11/05/2024 | N/A | Partial Pass | Contractor needs to finish planning the plants, the water harvesting and the riprap | |
11/05/2024 | N/A | Partial Pass | Contractor needs to finish planning the plants, the water harvesting and the riprap |
Completed Inspections
Permit Status: Issued
Permit Number: DP22-0145
Permit Description: *Revision #1 (shade canopy/grade) started 8/17/24.* Site/Grading - New community building and three new residence buildings.
Total Completed Inspections - 4
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/29/2023 | PDSD Engineering Division Pre-Construction SITE | Passed | -met with David Valencia PS, discussed stormwater controls, provided solid waste enclosure specs, requested track out cleanup on lee and Rook streets. | |
12/07/2023 | ENGR Grading Final | Passed | ||
12/28/2023 | COT - ENGR - Stormwater | Passed | ||
07/03/2024 | SITE - Sign Footer/Setback/Excavation Layout/Rebar | Passed |