Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: DP22-0010
Permit Details
Apply Date:
01/27/2022
Applicant:
William Shipley
Description:
*Revision #4 (updated plans) started 8/5/24* *Revision #3 (parking) started 5/2/24* *Revision 2 - Sanitary Sewer Services and Storm Drainage Connection // Site/Grading - CAP Bridges, indoor storage facility.
Permit Reviews
Permit Number - DP22-0010
Permit Status: Inspections
Permit Description: *Revision #4 (updated plans) started 8/5/24* *Revision #3 (parking) started 5/2/24* *Revision 2 - Sanitary Sewer Services and Storm Drainage Connection // Site/Grading - CAP Bridges, indoor storage facility.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/27/2022 | DEV PKG - OK TO SUBMIT | 02/07/2022 | COMPLETED |
02/07/2022 | DEV PKG | 04/19/2022 | COMPLETED |
06/23/2022 | DEV PKG - RESUBMITTAL | 08/15/2022 | COMPLETED |
06/09/2023 | DEVELOPMENT PACKAGE REVIEW v.1 | 06/20/2023 | REQUIRES RESUBMIT |
12/14/2022 | DEVELOPMENT PACKAGE REVIEW v.1 | 01/13/2023 | APPROVED |
07/12/2023 | DEVELOPMENT PACKAGE REVIEW v.2 | 08/09/2023 | REQUIRES RESUBMIT |
12/13/2023 | DEVELOPMENT PACKAGE NEW v.1 | 01/12/2024 | REQUIRES RESUBMIT |
08/28/2023 | DEVELOPMENT PACKAGE REVIEW v.3 | 10/06/2023 | APPROVED |
03/28/2024 | DEVELOPMENT PACKAGE NEW v.2 | 04/01/2024 | APPROVED |
08/05/2024 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 08/30/2024 | APPROVED |
07/30/2024 | DEVELOPMENT PACKAGE NEW v.2 | 08/02/2024 | APPROVED |
05/02/2024 | DEVELOPMENT PACKAGE NEW v.1 | 05/20/2024 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Inspections
Permit Number: DP22-0010
Permite Description: *Revision #4 (updated plans) started 8/5/24* *Revision #3 (parking) started 5/2/24* *Revision 2 - Sanitary Sewer Services and Storm Drainage Connection // Site/Grading - CAP Bridges, indoor storage facility.
Total Outstanding Inspections - 5
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/22/2024 | PDSD Site/Engineering Division - NPPO | N/A | Not Applicable | |
09/26/2024 | COT - FCON - Fire - Final | N/A | Not Applicable | |
04/16/2024 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | Dan Bishop would be FL contacted me to look at this site to verify that they are wanting to change the grades in the basin located on the west end of the project slightly since their concrete box structure is not at the correct grade and came in lower than expected. They will be submitting revised drawings to get approved showing the changes that will be made to the site. |
10/11/2024 | ENGR - Drainage Structures | N/A | Partial Pass | Pictures will be needed on the last two structures |
09/11/2024 | COT - ENGR - Stormwater | N/A | Partial Pass | Contractors installing 30 inch RCP’s on the west side of the building 120 feet ready to be backfilled |
Completed Inspections
Permit Status: Inspections
Permit Number: DP22-0010
Permit Description: *Revision #4 (updated plans) started 8/5/24* *Revision #3 (parking) started 5/2/24* *Revision 2 - Sanitary Sewer Services and Storm Drainage Connection // Site/Grading - CAP Bridges, indoor storage facility.
Total Completed Inspections - 5
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/30/2024 | PDSD Engineering Division Pre-Construction SITE | Passed | ||
02/22/2024 | SITE - Zoning Compliance | Passed | ||
02/22/2024 | COT - SITE - Zoning Intermediate | Passed | ||
02/22/2024 | SITE - SWPPP Violation Notice | Passed | ||
02/22/2024 | SITE - SWPPP Correction Notice | Passed |