Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Development Package
Address:
3372 S 6TH AV
Address NEW:
3372 S 6TH AV
Apply Date:
11/08/2021
Applicant:
Description:
SITE: Southgate Shopping Center, parking lot. Revise islands and pedestrian crossings.

Permit Reviews

Permit Number - DP21-0303
Permit Status: Issued
Permit Description: SITE: Southgate Shopping Center, parking lot. Revise islands and pedestrian crossings.
Start Date Submittal Complete Date Status  
06/24/2022 DEV PKG - RESUBMITTAL 08/08/2022 COMPLETED Review Details
08/22/2022 DEV PKG - RESUBMITTAL 09/28/2022 COMPLETED Review Details
10/05/2022 DEV PKG - RESUBMITTAL 10/19/2022 ACTIVE Review Details
11/08/2021 DEV PKG - OK TO SUBMIT 11/12/2021 COMPLETED Review Details
11/12/2021 DEV PKG 12/01/2021 COMPLETED Review Details
10/27/2022 DEVELOPMENT PACKAGE REVIEW v.1 11/28/2022 APPROVED Review Details

Completed Inspections

Permit Status: Issued
Permit Number: DP21-0303
Permit Description: SITE: Southgate Shopping Center, parking lot. Revise islands and pedestrian crossings.
Total Completed Inspections - 3
Date Description Inspector Results Comments
01/12/2024 PDSD Engineering Division Pre-Construction SITE Passed Completed Pre-Construction meeting on site with the General Contractor Superintendent David Lua # (480) 385-8239 and Sub Contractor Kyle # (602) 775-2972.

Total of 40 sq. ft. of asphalt patch back will be completed.

Concrete sidewalk and curb areas will have AB and concrete strength tested by 3rd party engineer.

Approximately (10) directional signs will require galvanized poles set in 2’ depth footers and will be called in under COT permit for inspection prior to installation.

Per David Lua the traffic control plan is expired and he will have barricade company re-submit prior to start of work.

David is requiring a Saturday inspection and will contact COT to schedule.
02/02/2024 ENGR Grading Final Passed 6 inch Vertical Separation has not been provided where the existing sidewalk and roadway are at the same level.
02/02/2024 ENGR Engineering Final Passed David with daily Marshall group at 480-385-8329