Inspection History Details
Inspection Status: Passed
Inspection History: PDSD Engineering Division Pre-Construction SITE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/12/2024 | PDSD Engineering Division Pre-Construction SITE | Passed | Completed Pre-Construction meeting on site with the General Contractor Superintendent David Lua # (480) 385-8239 and Sub Contractor Kyle # (602) 775-2972. Total of 40 sq. ft. of asphalt patch back will be completed. Concrete sidewalk and curb areas will have AB and concrete strength tested by 3rd party engineer. Approximately (10) directional signs will require galvanized poles set in 2’ depth footers and will be called in under COT permit for inspection prior to installation. Per David Lua the traffic control plan is expired and he will have barricade company re-submit prior to start of work. David is requiring a Saturday inspection and will contact COT to schedule. |