Permit: DP21-0303

Parcel: 11901076B


Addresses:

3372 S 6TH AV


Inspection Status: Passed

Inspection History: PDSD Engineering Division Pre-Construction SITE

Permit Number - DP21-0303

Inspection Description - PDSD Engineering Division Pre-Construction SITE

Inspection Status - Passed

Date Description Inspector Results Comments
01/12/2024 PDSD Engineering Division Pre-Construction SITE Passed Completed Pre-Construction meeting on site with the General Contractor Superintendent David Lua # (480) 385-8239 and Sub Contractor Kyle # (602) 775-2972.

Total of 40 sq. ft. of asphalt patch back will be completed.

Concrete sidewalk and curb areas will have AB and concrete strength tested by 3rd party engineer.

Approximately (10) directional signs will require galvanized poles set in 2’ depth footers and will be called in under COT permit for inspection prior to installation.

Per David Lua the traffic control plan is expired and he will have barricade company re-submit prior to start of work.

David is requiring a Saturday inspection and will contact COT to schedule.