Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: DP21-0179
Permit Details
Apply Date:
07/05/2021
Applicant:
Description:
Site/Grading - Fry's Fuel Center #58.
Permit Reviews
Permit Number - DP21-0179
Permit Status: Complete
Permit Description: Site/Grading - Fry's Fuel Center #58.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/28/2022 | DEV PKG - RESUBMITTAL | 04/15/2022 | COMPLETED |
07/05/2021 | DEV PKG - OK TO SUBMIT | 07/09/2021 | COMPLETED |
07/14/2021 | DEV PKG - OK TO SUBMIT | 07/16/2021 | COMPLETED |
07/16/2021 | DEV PKG | 09/08/2021 | COMPLETED |
10/01/2021 | DEV PKG - RESUBMITTAL | 11/19/2021 | COMPLETED |
06/02/2023 | DEVELOPMENT PACKAGE REVIEW v.4 | 12/04/2023 | APPROVED |
03/24/2023 | DEVELOPMENT PACKAGE REVIEW v.3 | 05/30/2023 | APPROVED |
02/09/2023 | DEVELOPMENT PACKAGE REVIEW v.2 | 03/03/2023 | REQUIRES RESUBMIT |
04/03/2024 | DEVELOPMENT PACKAGE REVIEW v.1 | 04/26/2024 | APPROVED |
01/13/2023 | DEVELOPMENT PACKAGE REVIEW v.1 | 01/13/2023 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Complete
Permit Number: DP21-0179
Permite Description: Site/Grading - Fry's Fuel Center #58.
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/04/2024 | ENGR - Drainage Structures | N/A | Not Applicable | |
06/04/2024 | PDSD Site/Engineering Division - Landscaping | N/A | Not Ready | |
06/04/2024 | PDSD Site/Engineering Division - NPPO | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: DP21-0179
Permit Description: Site/Grading - Fry's Fuel Center #58.
Total Completed Inspections - 9
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/04/2024 | COT - ENGR - Signage Final | Passed | ||
06/04/2024 | SITE - Stormwater Final Inspection | Passed | ||
06/04/2024 | SITE - Zoning Final | Passed | ||
06/04/2024 | City of Tucson (COT) Planning and Development Services Engineering (ENGR) Zoning Compliance Inspection | Passed | ||
06/04/2024 | COT - ENGR - Site - Assurance Release | Passed | ||
06/04/2024 | COT - ENGR - Stormwater | Passed | No other inspection needed | |
06/04/2024 | COT - SITE - Zoning Intermediate | Passed | ||
06/07/2024 | ENGR Engineering Final | Passed | ||
06/07/2024 | Final inspection to ensure all landscape and water harvesting SITE | Passed |