Permit: DP21-0130
Permit Details
Apply Date:
05/26/2021
Applicant:
Description:
Rev 1 - update to parking, curbs, landscape started 01.16.2026 ** Site/Grading - 1Ave Elm Homes. Units 1 through 5.
Permit Reviews
Permit Number - DP21-0130
Permit Status: Complete
Permit Description: Rev 1 - update to parking, curbs, landscape started 01.16.2026 ** Site/Grading - 1Ave Elm Homes. Units 1 through 5.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/26/2021 | DEV PKG - OK TO SUBMIT | 05/28/2021 | COMPLETED |
| 05/28/2021 | DEV PKG | 07/01/2021 | COMPLETED |
| 10/08/2021 | DEV PKG - RESUBMITTAL | 12/16/2021 | COMPLETED |
| 12/06/2022 | DEVELOPMENT PACKAGE REVIEW v.1 | 12/15/2022 | APPROVED |
| 01/16/2026 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 02/10/2026 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: DP21-0130
Permite Description: Rev 1 - update to parking, curbs, landscape started 01.16.2026 ** Site/Grading - 1Ave Elm Homes. Units 1 through 5.
Total Outstanding Inspections - 8
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | PDSD Site/Engineering Division - Landscaping | N/A | Not Ready | |
| 10/26/2022 | SITE - SWPPP Correction Notice | N/A | Not Ready | |
| 10/26/2022 | PDSD Site/Engineering Division - NPPO | N/A | Not Ready | |
| 10/26/2022 | SITE - Stormwater Follow-up | N/A | Not Ready | |
| 10/27/2022 | ENGR Grading Final | N/A | Not Ready | |
| 10/26/2022 | SITE - SWPPP Violation Notice | N/A | Not Ready | |
| 10/26/2022 | SITE - Stormwater Setup and Controls | N/A | Not Ready | |
| 04/09/2026 | COT - FCON - Fire - Final | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: DP21-0130
Permit Description: Rev 1 - update to parking, curbs, landscape started 01.16.2026 ** Site/Grading - 1Ave Elm Homes. Units 1 through 5.
Total Completed Inspections - 10
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/01/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | I informed the contractor that the downspouts coming off the roof drain needs sidewalk scupper so the water doesn’t run over the sidewalk. | |
| 02/26/2026 | Consultation SITE | Passed | Met onsite to review plans and inspection needs. | |
| 02/26/2026 | Final inspection to ensure all landscape and water harvesting SITE | Passed | Water harvesting areas are correct. Still need ground cover and curb cuts, will defer those two items to the Landscape Final and Engineering Final respectively. | |
| 04/09/2026 | Passed | All items related to parking, striping, and pedestrian circulation are complete in accordance with approved plans and ADA requirements. | ||
| 04/09/2026 | SITE - Stormwater Final Inspection | Passed | Site is stabilized and controls have been removed. | |
| 04/09/2026 | SITE - Zoning Final | Passed | Site is complete in accordance with zoning rules. | |
| 04/09/2026 | Passed | Sidewalk slopes are in compliance with necessary specifications. Sidewalks are in accordance with ADA requirements. | ||
| 04/09/2026 | ENGR Engineering Final | Passed | Development Package is complete in accordance with approved plans. | |
| 04/09/2026 | COT - ENGR - Signage Final | Passed | ||
| 04/09/2026 | ENGR Paving | Passed | Paving is complete in accordance with approved plans. |